HomeMy WebLinkAbout2012.10.02_Street Rehabilitation ProgramPROJECT COMPLETION REPORT
PROJECT:_ Street Rehabilitation Program (FY 2011-2012)
DATE PROJECT WAS INITIATED: March 16, 2012
DATE PROJECT WAS COMPLETED: October 2, 2012
DEPARTMENT RESPONSIBILITY FOR PROJECT:_ Public Works Department
STAFF COMMENTS: Included in FY 2011-2012 Budget the Capital Improvements
Fund allowed for the expenditure of $585,000 for the repair and /or resurfacing of
residential and non - residential roadways throughout the city. Phase I of the
rehabilitation program included pavement repair, foq seal micro -pave and
concrete curb and gutter replacement This work was performed by a private
contractor (Tri -Star Construction) in the amount of $359,428.95 an under run of
$8,630.25.
Phase II of the program was completed via a private- public partnership and
included the paving and /or surfacing of approximately two lane -miles (or 710
tons of asphalt) of roadway surface Tulsa County provided the labor and
equipment for the paving and /or resurfacing and the City purchased the
necessary materials. On August 3 2012 City Council approved the purchase of
asphalt material in the amount of $25,771.71. In addition other necessary
materials were purchased in the amount of $5,184.13. Total project expenditures
amounted to $390,384.79.
Roger Stevens, Public Works Director
DEPARTMENT
January 25, 2013
DATE
Approved this 28th day of January, 2013
Brenda Snow, Chairman