HomeMy WebLinkAbout2011.04_Street Improvement/Repair ProjectPROJECT COMPLETION REPORT
PROJECT: Street Improvement /Repair Project (FY 2010)
DATE PROJECT WAS INITIATED: July 2010
DATE PROJECT WAS COMPLETED: April 2011
DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department
STAFF COMMENTS: As in previous years, the FY 2010 Street Improvement /Repair
Project was completed via a joint partnership between the City of Owasso and Tulsa
County for the repair and /or resurfacing of residential and non - residential roadways
throughout the city. In July 2010, the City Council approved the following street
treet
repair priorities: E .1 16th Street North and N. Garnett Road Intersection and N. 126th
East Avenue from E. 86th Place North to E. 87th Street North. On September 7, 2010,
the City Council awarded the construction contract to Tri -Star Construction, LLC in
the amount of $250,610 for the necessary base repair on both locations and the
asphalt overlay on the N. 126th East Avenue location. Tulsa County crews performed
the asphalt overlay on the E. 116th Street North and N. Garnett Road Intersection
location. In April 2011, the City Council accepted the street improvements and
approved final payment bringing the total contract amount to $219,120.20 an
under run of $31,489.80). Including the purchase of asphalt material in the amount
of $16,918, the total project cost is $236,038.
Roger Steven , Public Works Director
July 25, 2011
DATE
Approvep this 25th day of July, 2011.
Brenda Snow, Chai