HomeMy WebLinkAbout2010.07.15_Tulsa Technology Center/Tulsa Community College Road ConstructionPROJECT COMPLETION REPORT
PROJECT: Tulsa Technology Center /Tulsa Community College Road Construction
Project
DATE PROJECT WAS INITIATED: July 15, 2008
DATE PROJECT WAS COMPLETED: July l5, 2010
DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department
STAFF COMMENTS: The broiect consists of
000 feet north
from E 116 "' St. North to the south The existing segment (1,324 feet) served QuikTrip,
Eggbert's restaurant, and future development parcels. On July 15 2008 the City Council
awarded an engineering agreement in the amount of $162,500 to Craft Tull Sparks. The
engineering design was completed in May 2009. On July 21 2009 the City Council
awarded the construction contract to Becco Construction in the amount of $1,566,682.
On July 15, 2010, the City Council accepted the completed project and approved the final
payment to Becco Construction in the amount of $631.616.42 for a total contract price of
$1,388,293.20, resulting in an under -run of $178,389. Total project cost including
engineering design fees, miscellaneous, and construction equals $1,559,679.
Roger Stevens
PROJECT COORDINATOR
Public Works
DEPARTMENT
January 24, 2011
DATE
this 18th day of January, 2011.
Brenda Snow, C