Loading...
HomeMy WebLinkAbout2010.04.12._Sports Park South Phase I Water Line ImprovementsPROJECT COMPLETION REPORT PROJECT: Sports Park South — Phase I Water Line Improvements DATE PROJECT WAS INITIATED: January 1, 2010 DATE PROJECT WAS COMPLETED: April 12, 2010 DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department STAFF COMMENTS: City staff designed and installed 2,000 linear feet of 8" water line in order to provide adequate capacity for current and future irrigation and potable usage on the south end of the Sports Park. Construction of the waterline improvements was performed by city staff for a total cost of $22,252.70. Roger Stevens PROJECT COORDINATOR Public Works DEPARTMENT July 23, 2010 DATE Approved this 26th day of July, 2010. StweeMowery, Vic airman