PROJECT: Sports Park South — Phase I Water Line Improvements
DATE PROJECT WAS INITIATED: January 1, 2010
DATE PROJECT WAS COMPLETED: April 12, 2010
DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department
STAFF COMMENTS: City staff designed and installed 2,000 linear feet of 8" water
line in order to provide adequate capacity for current and future irrigation and potable usage
on the south end of the Sports Park. Construction of the waterline improvements was
performed by city staff for a total cost of $22,252.70.