HomeMy WebLinkAbout2004.06.15_E 86th Street North ImprovementsSUPPLEMENTAL
PROJECT COMPLETION REPORT
PROJECT:_ E. 86th Street North Improvements
DATE PROJECT WAS INITIATED: September 2, 2003
DATE PROJECT WAS COMPLETED: June 15, 2004 * see supplemental below
DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department
STAFF COMMENTS: E. 86th Street North Improvements (from N 129th East Avenue to N.
145th East Avenue) which involves the widening of the street to five lanes, construction of
new sidewalk, curb and gutter and signalization at 8th Grade Center. On August 5 2003
City Council awarded the construction contract to Becco Construction Inc. Tulsa OK in the
total amount of $2,472,065.20. Three change orders were issued during construction in the
amount of $188,447.44. Final construction cost for the project was $2,660,5 12.64.
Supplemental Information:
Including expenses for right of way acquisition utility relocations engineering and design
and all other costs, the total project was $3,303,741 as of December 31, 2005. The original
CProject Completion Report was approved by the Watchdog Committee on January 24 2005.
One item related to right of way clearance, the demolition of a barn, remained outstanding_.
The barn has been demolished and removed from the property at a cost of $15,500. Final
orth
Rozer Stevens
PROJECT COORDINATOR
Public Works
DEPARTMENT
January 25, 2010
DATE
Approv d this 25TH day of January, 2010.
Bre d Snow, Chair