HomeMy WebLinkAbout2004.06.15_E 86th Street North ImprovementsSUPPLEMENTAL PROJECT COMPLETION REPORT PROJECT:_ E. 86th Street North Improvements DATE PROJECT WAS INITIATED: September 2, 2003 DATE PROJECT WAS COMPLETED: June 15, 2004 * see supplemental below DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department STAFF COMMENTS: E. 86th Street North Improvements (from N 129th East Avenue to N. 145th East Avenue) which involves the widening of the street to five lanes, construction of new sidewalk, curb and gutter and signalization at 8th Grade Center. On August 5 2003 City Council awarded the construction contract to Becco Construction Inc. Tulsa OK in the total amount of $2,472,065.20. Three change orders were issued during construction in the amount of $188,447.44. Final construction cost for the project was $2,660,5 12.64. Supplemental Information: Including expenses for right of way acquisition utility relocations engineering and design and all other costs, the total project was $3,303,741 as of December 31, 2005. The original CProject Completion Report was approved by the Watchdog Committee on January 24 2005. One item related to right of way clearance, the demolition of a barn, remained outstanding_. The barn has been demolished and removed from the property at a cost of $15,500. Final orth Rozer Stevens PROJECT COORDINATOR Public Works DEPARTMENT January 25, 2010 DATE Approv d this 25TH day of January, 2010. Bre d Snow, Chair