HomeMy WebLinkAbout2014.10.21_OPWA AgendaPUBLIC NOTICE THE MEETING OF THE
OWASSO PUBLICFWORKS AUTHORITY R�G�\��O
1p J
Council Chambers, Old Central Building g
109 N Birch, Owasso, OK 74055 041
Regular Meeting 0M
Tuesday, October 21, 2014 - 6:30 pm
1. Call to Order
Chairman Jeri Moberly
2. Roll Call
3. Consideration and appropriate action relating to a request for approval of the Consent
Agenda. All matters listed under "Consent" are considered by the Trustees to be routine and
will be enacted by one motion. Any Trustee may, however, remove an item from the Consent
Agenda by request. A motion to adopt the Consent Agenda is non - debatable.
A. Approve minutes
• October 7, 2014 Regular Meeting
• October 14, 2014 Regular Meeting
B. Approve claims
C. Receive monthly budget status report
4. Consideration and appropriate action relating to items removed from the Consent Agenda
5. Consideration and appropriate action relating to an engineering services agreement for the
Wastewater Masterplan Update
Roger Stevens
Staff recommends approval of the agreement with Greeley and Hansen LLC in the amount
of $118,000.
6. Report from OPWA Manager
7. Report from OPWA Attorney
8. New Business (New Business is any item of business which could not have been foreseen at
the time of posting of the agenda)
9. Adjournment
Notice of Public Meeting filed in the office of the City Clerk and Agenda posted at City Hall
bulletin board at 6:00 pm on Friday, October 17, 2014.
iff'/Gml-
Sherry Bishop; City Clerk
OWASSO PUBLIC WORKS AUTHORITY
MINUTES OF REGULAR MEETING
Tuesday, October 7, 2014
The Owasso Public Works Authority met in regular session on Tuesday, October 7, 2014 in the
Council Chambers at Old Central per the Notice of Public Meeting and Agenda filed in the
office of the City Clerk and posted on the City Hall bulletin board at 6:00 pm on Friday, October
3, 2014 and the Addendum filed in the office of the City Clerk and posted on the City Hall
bulletin board at 5:00 pm on Monday, October 6, 2014.
1. Call to Order
Vice - Chairman Lyndell Dunn called the meeting to order at 7:37 pm.
2. Roll Call
Present
Vice - Chairman - Lyndell Dunn
Trustee - Doug Bonebrake
Trustee - Bill Bush
Trustee - Chris Kelley
A quorum was declared present.
Staff:
Authority Manager - Warren Lehr
Authority Attorney - Julie Lombardi
Absent
Chairman - Jeri Moberly
3. Consideration and appropriate action relating to a request for approval of the Consent
Agenda. All matters listed under "Consent" are considered by the Trustees to be routine and
will be enacted by one motion. Any Trustee may, however, remove an item from the Consent
Agenda by request. A motion to adopt the Consent Agenda is non - debatable.
A. Approve minutes - September 16, 2014 Regular Meeting
B. Approve claims
Dr. Kelley moved, seconded by Mr. Bonebrake to approve the Consent Agenda with claims
totaling $703,397.43. Also, included for review was the payroll report for 9/20/14.
YEA: Bonebrake, Bush, Kelley, Dunn
NAY: None
Motion carried: 4 -0
4. Consideration and appropriate action relating to items removed from the Consent Agenda
None
5. Consideration and appropriate action relating to a Development Agreement between the
City of Owasso, Owasso Public Works Authority, and Owasso Investment Partners, LLC for
limited purposes set forth in the Agreement and authorization for the execution of said
Agreement
Chelsea Levo presented the item recommending approval of the proposed agreement.
Owasso Public Works Authority
October 7, 2014
Page 2
After discussion, Mr. Bush moved, seconded by Mr. Bonebrake to approve the development
agreement, as recommended.
YEA: Bonebrake, Bush, Kelley, Dunn
NAY: None
Motion carried: 4 -0
6. Report from OPWA Manager
None
7. Report from OPWA Attorney
None
8. New Business
None
9. Adjournment
Mr. Bonebrake moved, seconded by Dr. Kelley to adjourn the meeting.
YEA: Bonebrake, Bush, Kelley, Dunn
NAY: None
Motion carried 4 -0 and the meeting adjourned at 7:38 pm.
Lyndell Dunn, Vice - Chairman
Lisa Wilson, Minute Clerk
OWASSO CITY COUNCIL, OPWA, AND OPGA
MINUTES OF JOINT REGULAR MEETING
Tuesday, October 14, 2014
The Owasso City Council, Owasso Public Works Authority, and Owasso Public Golf Authority met
in joint regular meeting on Tuesday, October 14, 2014 in the Council Chambers at Old Central,
109 N Birch Street, per the Notice of Public Meetings filed in the City Clerk's office on December
15, 2014 and the Agenda posted on the City Hall bulletin board at 6:00 pm on Friday, October
10, 2014.
ITEM 1: CALL TO ORDER
Mayor Jeri Moberly called the meeting to order at 6:00 pm
PRESENT ABSENT
Jeri Moberly, Mayor /Chairman None
Lyndell Dunn Vice Mayor /Vice Chairman
Bill Bush, Councilor /Trustee
Doug Bonebrake, Councilor /Trustee
Chris Kelley, Councilor /Trustee
A quorum was declared present.
ITEM 2: PRESENTATION AND DISCUSSION RELATING TO SELF- INSURANCE
Michele Dempster provided an overview of the city's self - insurance funds and discussion was
held. It was further explained that a request to execute a renewal contract for specific excess
workers' compensation insurance as well as property casualty coverage will be placed on the
October 21, 2014 Council Consent Agenda.
ITEM 3: DISCUSSION RELATING TO COMMUNITY DEVELOPMENT ITEMS
A. Plat vacation - Owasso Freewill Baptist Church
B. Final plat - Rejoice Christian Campus
C. Platvacation - TheSevens
D. Re- plat /Finalplat - TheSevens
E. Final plat- Lake Valley V, Phase II
F. Final plat - K -MAC (NW corner, west of McDonald's at 11 61h St N & 135th E Ave)
Bronce Stephenson presented each planning item and discussion was held. It was explained
that each item would be placed on the October 21, 2014 Council Agenda for consideration
and action.
ITEM 4: DISCUSSION RELATING TO THE 2015 TULSA REGIONAL CHAMBER ONEVOICE LEGISLATIVE
AGENDA
John Feary presented the item and discussion was held. It was further explained that a
resolution item would be placed on the October 21, 2014 Council Agenda for consideration and
action.
ITEM 5: DISCUSSION RELATING TO FINANCE ITEMS
A. Capital Improvement Projects Funding timeline
B. OPGA Cash Balance
Linda Jones presented each item and discussion was held. Under Item B, Ms. Jones presented
staff's plan to reduce the negative fund balance in the OPGA fund and that future budgets will
include implementation of this plan.
October 14, 2014
Page 2
ITEM 6: DISCUSSION RELATING TO PUBLIC WORKS ITEMS
A. Engineer agreement- Wastewater Masterplan Update
B. Engineer agreement- Brookfield Crossing Stormwater Improvements
Roger Stevens presented each item and discussion was held. It was further explained that each
item will be placed on the October 21, 2014 agenda for consideration and action; Item A on the
Council Agenda and Item B on the OPWA Agenda.
ITEM 7: DISCUSSION RELATING TO RENEWAL OF YOUTH COURT CONTRACT
Julie Lombardi presented the item and discussion was held. It was further explained that an item
will be listed on the October 21, 2014 Council Consent Agenda for consideration and
appropriate action.
ITEM 8: CONSIDERATION AND APPROPRIATE ACTION RELATING TO A REQUEST FOR AN EXECUTIVE
SESSION FOR PURPOSES OF DISCUSSING CONFIDENTIAL COMMUNICATIONS BETWEEN THE
CITY COUNCIL AND THE CITY ATTORNEY CONCERNING PENDING LITIGATION AS
PROVIDED FOR IN TITLE 25, O.S. SECTION § 307(B)(4)
Councilor Bush moved, seconded by Councilor Bonebrake to enter into executive session for the
purpose of discussing pending litigation.
YEA: Bonebrake, Bush, Dunn, Kelley, Moberly
NAY: None
Motion carried 5 -0 and the City Council, Julie Lombardi, and Warren Lehr, entered into
executive session at 8:34 pm.
At 9:20 pm, the City Council returned to open session.
ITEM 9: DISCUSSION RELATING TO CITY MANAGER ITEMS
• '/2 Penny Sales Tax election
• Monthly Sales Tax Report
• City Manager Report
Warren Lehr presented draft language for the Ordinance and Resolution related to the proposal
to seek voter approval to increase the sales tax rate by '/2 percent and restrict the use of the
funds for Police, Fire, and Streets and discussion was held.
Linda Jones presented the monthly sales tax report and discussion was held.
Under the City Manager Report, Mr. Lehr commented on the status of Surface Transportation
Funding for roadway improvements; Rayola Park Grand Opening is scheduled for October 251h
at 11:OOam; the Vision 2025 process for disbursing excess funds is nearly finalized; and discussions
with the Tulsa County Criminal Justice Authority regarding jail fees are progressing.
ITEM 10: CITY COUNCIL /TRUSTEE COMMENTS AND INQUIRIES
Mayor Moberly reported on recent action taken by the INCOG Board of Directors to endorse the
Bird Creek bridge improvement project on HWY 169 in the amount of $30,364,510.
ITEM 11: ADJOURNMENT
Councilor Bush moved, seconded by Councilor Kelley to adjourn the meeting.
YEA: Bonebrake, Bush, Dunn, Kelley, Moberly
NAY: None
Motion carried 5 -0 and the meeting adjourned at 10:06 pm.
Jeri Moberly, Mayor /Chairman
Juliann M. Stevens, Minute Clerk
Claims List
10/21/2014
Budget Unit Title
Vendor Name
Payable Description
Payment Amount
OPWA ADMINISTRATION
JPMORGAN CHASE BANK
INTERSTATE - BATTERIES
35.45
OWASSO CHARACTER COUNCIL, INC
2014 CHARACTER LUNCHEON
35.00
JPMORGAN CHASE BANK
LODGING EXPENSE /STEVENS
484.73
TREASURER PETTY CASH
CAB FARES /STEVENS
80.00
JPMORGAN CHASE BANK
LOWES -LIGHT BULBS
44.98
ONEOK, INC OKLAHOMA NATURAL GAS
NATURAL GAS USAGE
82.64
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
44.16
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
42.16
BLUE ENERGY FUELS, LLC
CNG FUEL PURCHASES - SEPT
109.46
CITY GARAGE
LABOR/OVERHEAD- OCTOBER,
250.00
AT &T LONG DISTANCE
LONG DISTANCE SERVICE
167.47
JPMORGAN CHASE BANK
TRAVEL EXPENSE
6.95
JPMORGAN CHASE BANK
TRAVEL EXPENSE
12.57
JPMORGAN CHASE BANK
TRAVEL EXPENSE
51.88
JPMORGAN CHASE BANK I
TRAVEL EXPENSE
14.82
TOTAL OPWA ADMINISTRATION 1,462.27
UTILITY BILLING
JPMORGAN CHASE BANK
ADMIRAL EXP -TONER
83.11
TECHNICAL PROGRAMMING SERVICES INC
BILLING SERVICES
2,579.13
KATHLEEN A BALSIGER
METER READER
149.40
TODD C. KIMBALL
METER READER
478.35
KATHLEEN A BALSIGER
METER READER
564.30
TYRONE EUGENE DINKINS
METER READER
293.85
TOTAL UTILITY BILLING 4,148.14
WATER
VERDIGRIS VALLEY ELECTRIC COOP
WATER CONTROL ELECTRIC
30.60
FLEETCOR TECHNOLOGIES
FUELMAN EXPENSES - SEPT,
1,546.14
CITY GARAGE
VEH PARTS PURCH - SEPT
121.20
CITY GARAGE
LABORIOVERHEAD.- OCTOBER,
1,751.24
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
60.82
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
60.82
DOLESE BROS CO.
CONCRETE
372.00
OWASSO TOP SOIL
TWO LOADS OF YARD DIRT
65.00
JPMORGAN CHASE BANK
BROWN FARMS-SOD
90.00
JPMORGAN CHASE BANK
BROWN FARMS-SOD
55.00
JPMORGAN CHASE BANK
NORTHERN SAFETY - APPAREL
213.26
CITY OF TULSA UTILITIES
WATER
86,718.75
CITY OF TULSA UTILITIES
WATER
159,340.26
JPMORGAN CHASE BANK
jQUALrFY TIRE - ALIGNMENT
69.95
TOTAL WATER 250,495.04
WASTEWATER TREATMENT
JPMORGAN CHASE BANK
AIR MAC - BLOWER REPAIR
500.00
JPMORGAN CHASE BANK
OREILLYS -FUSES
16.47
Page 1
Claims List
10/21/2014
Budget Unit Title
Vendor Name
Payable Description
PaymentAmount
WASTEWATER TREATMENT..
JPMORGAN CHASE BANK
GRAINGER- INSPECTION LIGHT
57.96
JPMORGAN CHASE BANK
AIR MAC - BLOWER REPAIR
2,357.25
SCHREIBER, LLC
RH & LH PIN GUIDES
77.00
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
70.52
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
61.19
CITY GARAGE
LABORIOVERHEAD - OCTOBER,
361.78
CITY GARAGE
VEH PARTS PURCH -SEPT
1,046.52
FLEETCOR TECHNOLOGIES
FUELMAN EXPENSES - SEPT,
621.38
AT &T LONG DISTANCE
LONG DISTANCE SERVICE
74.44
JPMORGAN CHASE BANK
EQUIPMENT ONE -GAS LINE
15.46
JPMORGAN CHASE BANK
EQUIPMENT ONE -PARTS
19.50
JPMORGAN CHASE BANK
SW TRAILERS -PARTS
131.11
JPMORGAN CHASE BANK
HACH CO- TUBING
133.79
JPMORGAN CHASE BANK
HACH CO -LAB SUPPLIES
205.69
VERIZON WIRELESS
WIRELESS CONNECTION
80.02
JPMORGAN CHASE BANK
SUPERIOR VALVE -VALVE
74.45
JPMORGAN CHASE BANK
GREEN ACRE SOD -PEA GRAVEL
120.00
JPMORGAN CHASE BANK IGREEN
ACRE SOD -PEA GRAVEL
240.00
TOTAL WASTEWATER TREATMENT 6,264.53
WASTEWATER COLLECTION:
JPMORGAN CHASE BANK
HD SUPPLY -PARTS
242.28
JPMORGAN CHASE BANK
HD SUPPLY - SUPPLIES
288.50
JPMORGAN CHASE BANK
HD SUPPLY -PARTS
33.60
JPMORGAN CHASE BANK
QUALITY TIRE -TIRE
212.50
JPMORGAN CHASE BANK
TRAVEL EXPENSE
14.57
JPMORGAN CHASE BANK
TRAVEL EXPENSE
11.97
JPMORGAN CHASE BANK
LODGING EXPENSEIBLUNDELL
484.72
JPMORGAN CHASE BANK
BROWN FARMS -SOD
55.00
VERDIGRIS VALLEY ELECTRIC COOP
COFFEE CREEK ELECTRIC
626.16
VERDIGRIS VALLEY ELECTRIC COOP
GARRETT CREEK ELECTRIC
162.96
VERDIGRIS VALLEY ELECTRIC COOP
GARRETT CREEK ELECTRIC
240.28
FLEETCOR TECHNOLOGIES
FUELMAN EXPENSES - SEPT,
892.77
CITY GARAGE
VEH PARTS PURCH -SEPT
981.87
CITY GARAGE
LABOR/OVERHEAD - OCTOBER,
836.86
BLUE ENERGY FUELS, LLC
CNG FUEL PURCHASES - SEPT
298.56
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
45.70
ONEOK, INC OKLAHOMA NATURAL GAS
NATURAL GAS USAGE
150.08
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
72.24
JPMORGAN CHASE BANK
OREILLYS -FUSES
7.98
JPMORGAN CHASE BANK
ITRAVELEXPENSE
35.10
TOTAL WASTEWATER COLLECTIONS 5,693.70
RANCH CREEK INTERCEPTOI
ROSETTA CONSTRUCTION, LLC
1CONSTRU77ION SERVICES
187,870.93
Page 2
Claims List
10/21/2014
Budget Unit Title I
Vendor Name
Payable Description IPayment
Amount
TOTAL RANCH CREEK INTERCEPTOR 187,870.93
HALES ACRES SEW LINE REf TRIANGLE CONST 1CONSTRUCTION SERVICES 84,749.97
TOTAL HALES ACRES SEW LINE REPL 84,749.97
REFUSE COLLECTIONS
FLEETCOR TECHNOLOGIES
FUELMAN EXPENSES - SEPT,
6,848.90
JPMORGAN CHASE BANK
FASTENAL -PARTS
2.58
JPMORGAN CHASE BANK
TULSA CLEANING - REPAIRS
486.63
JPMORGAN CHASE BANK
KIM'S INT'L -HYDRA HOSES
120.14
VERIZON WIRELESS
WIRELESS CONNECTION
29.65
JPMORGAN CHASE BANK
GELLCOSAFETY BOOTS
98.99
JPMORGAN CHASE BANK
BUMPER2BUMPER -PARTS
36.00
JPMORGAN CHASE BANK
COT CNG -CNG FUEL
49.25
JPMORGAN CHASE BANK
BUMPER2BUMPER- GREASE
4.50
JPMORGAN CHASE BANK
MAC'S- CYLINDER REBUILD
599.75
CITY GARAGE
VEH PARTS PURCH -SEPT
1,645.21
BLUE ENERGY FUELS, LLC
CNG FUEL PURCHASES - SEPT
1,374.93
MCNEILUS FINANCIAL INC
BELTASSEMBLY
145.06
CITY GARAGE
LABOR/OVERHEAD - OCTOBER,
4,055.58
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
45.31
COVANTA LANCASTER, INC
REFUSE TIPPING FEES
4,693.51
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
45.31
JPMORGAN CHASE BANK
BUMPER28UMPER -STEER FLUID
7.70
JPMORGAN CHASE BANK
BUMPER2BUMPER- SOCKET
5.49
JPMORGAN CHASE BANK
BUMPER28UMPER -PLUG TAP
5.68
JPMORGAN CHASE BANK
MOTOROLA -RADIO REPAIR
465.00
TOTAL REFUSE COLLECTIONS 20,765.17
RECYCLE CENTER
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
10.98
UNIFIRST HOLDINGS LP
UNIFORM CLEANING
10.98
ZEE MEDICAL, INC
FIRST AID SUPPLIES
116.45
NATIONAL WASTE & DISPOSAL, INC.
GLASS ROLLOFFS X 2
400.00
CITY GARAGE
LABOR/OVERHEAD - OCTOBER,
47.71
CITY GARAGE
VEH PARTS PURCH -SEPT
269.54
JPMORGAN CHASE BANK
WASTE MGMT -REC TIP FEES
1,453.77
TOTAL RECYCLE CENTER 2,309.43
563,759.1
FUND GRAND TOTAL
OPWA GRAND TOTAL $563,759.18
Page 3
Department
OPWA Administration
Utility Billing
Water
Wastewater
Wastewater Collection
Ranch Creek Interceptor
Refuse
Recycle Center
OWASSO PUBLIC WORKS AUTHORITY
PAYROLL PAYMENT REPORT
PAY PERIOD ENDING DATE 10/04/14
Payroll Expenses Total Expenses
9,610.41
4,906.41
13,373.96
11,624.11
7,553.06
1,625.00
11,310.22
1,064.00
13,832.73
8,677.55
21,927.50
19,850.97
12,304.07
1,808.30
17,665.13
2,017.47
FUND TOTAL 61,067.17 98,083.72
OWASSO PUBLIC WORKS AUTHORITY - OPERATING FUND
FISCAL YEAR 2014 -2015
Budgetary Basis
Statement of Revenues & Expenses
As of September 30, 2014
MONTH
TO -DATE
OPERATING REVENUES:
Water
Wastewater
Refuse & recycle
Otherfees
Interest & other
TOTAL OPERATING REVENUES
OPERATING EXPENSES:
Personal services
Materials & supplies
Other services
Capital outlay
Debt service
TOTAL OPERATING EXPENSES
OPERATING REVENUES OVER EXPENSES
NONOPERATING REVENUES (EXPENSES)
Intergovernmental Revenue
Transfers in
Transfers out
TOTALTRANSFERS
YEAR
TO -DATE BUDGET
$ 490,735 $
1,434,729 $
5,050,000
309,462
910,195
3,653,950
158,356
489,247
1,854,000
27,771
111,601
571,400
1,415
205,333
218,937
$ 987,739 $
3,151,106 $
11, 348,287
$ 194,116 $
540,361 $
2,415,517
468,869
1,063,724
4,026,010
121,260
468,105
1,729,352
30,052
60,944
1,473,040
471,949
1,176,170
3,629,697
$ 1,286,246 $
3,309,304 $
13,273,616
$ (298,506) $ (158,198) $ (1,925,329)
114,550 114,550 248,734
(100,000) (100,000) (400,000)
$ 14,550 $ 14,550 $ (151,266)
OWRB PROCEEDS AND EXPENDITURES
Proceeds of OWRB debt $ 497,871 $ 497,871 $ 1,386,992
Expenditures of OWRB Debt (194,953) (499,734) (1,386,992)
TOTAL OWRB PROCEEDS AND EXPENDITURES $ 302,917 $ (1,864) $ (0)
NET INCOME (LOSS)
$ 18,961 $
(145,512)
$
(2,076,595)
WORKING CAPITAL- Beginning Balance
$
2,431,574
$
2,431,574
WORKING CAPITAL - Ending Balance
$
2,286,062
$
354,979
PERCENT
OF BUDGET
28.41%
24.91%
26.39%
19.53%
93.79%
27.77%
22.37%
26.42%
27.07%
4.14%
32.40%
24.93%
46.05%
25.00%
O—T city Wit out Limits.
TO:
The Honorable Chair and Trustees
Owasso Public Works Authority
FROM:
Roger Stevens
Public Works Director
SUBJECT:
Agreement for Engineering Services
Wastewater Master Plan Update
DATE:
October 17, 2014
BACKGROUND
The City of Owasso provides wastewater collection, conveyance and treatment services for
over 9,500 residential, business and industrial customers. The existing collection system consists of
over 175 miles of sanitary sewer line (ranging in size from 4 to 30 inches in diameter), 12 pump
stations and a 4.2 million gallon per day (MGD) treatment facility.
In response to rapid growth, in 2005 the City of Owasso commissioned the update of its 1997
Wastewater Master Plan. The update provided a 20 -year guide for developing the necessary
facilities and improvements to satisfy wastewater collection and treatment needs for the existing
and future service area. A key element of the plan was to provide for orderly infrastructure
improvements, expansion and upgrading.
Since 2005, the City has experienced a higher density of growth in areas covered in the 2005
master plan update. In addition, wastewater treatment discharge limits governed by
Environmental Protection Agency and Oklahoma Department of Environmental Quality
continue to become more stringent possibly requiring upgrades at the wastewater treatment
facility. As a result, an update of the plan is proposed to more adequately reflect current
conditions and establish wastewater infrastructure requirements for a new 20 -year planning
period.
ENGINEERING SERVICES AGREEMENT:
In August 2014, staff requested a proposal from Greeley and Hansen LLC of Chicago, Illinois.
Based upon Greeley and Hansen updating the master plan in 2005, designing multiple
wastewater projects for the OPWA and fee negotiations, Greeley and Hansen LLC is being
recommended as the design engineer for the project.
Key provisions in the planning process will provide the following elements
• Update wastewater model with the new improvements to the wastewater collection
system;
• Hydraulic modeling of the existing system to provide a basis for evaluating and
projecting operational improvements;
• Review potential NPDES permit requirements;
• ODEQ coordination;
• Future system expansion will be evaluated for planned development and projections for
years 2020, 2025, 2030 and ultimate buildout conditions; and
• Implementation schedule.
FUNDING:
Funding in the amount of $120,000 is included in the FY 2015 Wastewater Treatment Plant Budget
for the engineering services for the Wastewater Master Plan Update.
RECOMMENDATION:
Staff recommends approval of an engineering services agreement with Greeley and Hansen
LLC in the amount of $118,000 for the update to the Wastewater Master Plan.
ATTACHMENT:
Engineering Service Agreement
Agreement for Professional Engineering Services
between
Owasso Public Works Authority Owasso, Oklahoma
and
Greeley and Hansen LLC
THIS AGREEMENT, made and entered into this October 21, 2014 between the Owasso Public Works
Authority, Owasso, Oklahoma, a Municipal Corporation, of Oklahoma, hereinafter referred to as
AUTHORITY, and Greeley and Hansen LLC, hereinafter referred to as ENGINEER;
WITNESSETH:
WHEREAS, AUTHORITY intends to complete the Wastewater Master Plan Update, hereinafter referred to
as the PROJECT; and,
WHEREAS, AUTHORITY requires certain professional services in connection with the PROJECT,
hereinafter referred to as the SERVICES; and,
WHEREAS, ENGINEER, is prepared to provide such SERVICES;
NOW THEREFORE, in consideration of the promises contained herein, the parties hereto agree as follows:
1. SCOPE OF PROJECT. The scope of the PROJECT is described in Attachment A, SCOPE OF
PROJECT, which is attached hereto and incorporated by reference as part of this AGREEMENT.
2. SERVICES TO BE PERFORMED BY ENGINEER. ENGINEER shall perform the SERVICES
described in Attachment B, SCOPE OF SERVICES, which is attached hereto and incorporated by
reference as part of this AGREEMENT.
3. AUTHORITY'S RESPONSIBILITIES. AUTHORITY shall be responsible for all matters
described in Attachment C, RESPONSIBILITIES OF THE AUTHORITY, which is attached
hereto and incorporated by reference as part of this AGREEMENT.
4. COMPENSATION. AUTHORITY shall pay ENGINEER in accordance with Attachment D,
COMPENSATION, and further described in Attachment E, FEE /MANHOUR BREAKDOWN,
which are attached hereto and incorporated by reference as part of this AGREEMENT.
5. SCHEDULE. ENGINEER shall perform the SERVICES described in Attachment B, SCOPE OF
SERVICES, in accordance with the schedule set forth in Attachment F, SCHEDULE, attached hereto
and incorporated by reference as part of this AGREEMENT.
6. STANDARD OF PERFORMANCE. ENGINEER shall perform the SERVICES undertaken in a
manner consistent with the prevailing accepted standard for similar services with respect to projects of
comparable function and complexity and with the applicable laws and
AGREEMENT FOR ENGINEERING- MASTER PLAN
regulations published and in effect at the time of performance of the SERVICES. The PROJECT shall
be designed and engineered in a good and workmanlike manner and in strict accordance with this
AGREEMENT. All engineering work shall be performed by or under the supervision of Professional
Engineers licensed in the State of Oklahoma, and properly qualified to perform such engineering
services, which qualification shall be subject to review by AUTHORITY. Other than the obligation of
the ENGINEER to perform in accordance with the foregoing standards, no warranty, either express or
implied, shall apply to the SERVICES to be performed by the ENGINEER pursuant to this
AGREEMENT or the suitability of ENGINEER'S work product.
7. LIMITATION OF RESPONSIBILITY.
7.1. ENGINEER shall not be responsible for construction means, methods, techniques,
sequences, procedures, or safety precautions and programs in connection with the
PROJECT.
7.2. The presence of ENGINEER's personnel at a construction site is for the purpose of providing
to the AUTHORITY a greater degree of confidence that the completed construction work
will conform generally to the construction documents and that the integrity of the design
concept as reflected in the construction documents has been implemented and preserved by
the construction contractor(s).
7.3. In soils, foundation, groundwater, and other subsurface investigations, the actual
characteristics may vary significantly between successive test points and sample intervals
and at locations other than where observations, exploration, and investigations have been
made. Because of the inherent uncertainties in subsurface evaluations, changed or
unanticipated underground conditions may occur that could affect total PROJECT cost
and /or execution. These conditions and cost /execution effects are not the responsibility of
ENGINEER.
7.4. Record drawings will be prepared, in part, on the basis of information compiled and
furnished by others, and may not always represent the exact location, type of various
components, or exact manner in which the PROJECT was finally constructed. ENGINEER is
not responsible for any errors or omissions in the information from others that is
incorporated into the record drawings.
7.5. ENGINEER's deliverables, including record drawings, are limited to the sealed and signed
hard copies. Computer - generated drawing files furnished by ENGINEER are for
AUTHORITY or others' convenience. Any conclusions or information derived or obtained
from these files will be at user's sole risk.
8. OPINIONS OF COST AND SCHEDULE.
8.1. Since ENGINEER has no control over the cost of labor, materials, equipment, or services
furnished by others, or over contractors', subcontractors', or vendors' methods of
determining prices, or over competitive bidding or market conditions, ENGINEER'S cost
estimates shall be made on the basis of qualifications and experience as a Professional
Engineer.
8.2. Since ENGINEER has no control over the resources provided by others to meet
construction contract schedules, ENGINEER'S forecast schedules shall be made on the
basis of qualifications and experience as a Professional Engineer.
9. INTENTIONALLY BLANK
AGREEMENT FOR ENGINEERING - MASTER PLAN
10. LIABILITY AND INDEMNIFICATION.
10.1. ENGINEER shall indemnify AUTHORITY from and against legal liability for damages
arising out of the performance of the SERVICES for AUTHORITY, including but not limited
to any claims, costs, attorney fees, or other expenses of whatever nature where such liability
is caused by the negligent act, error, or omission of ENGINEER, or any person or
organization for whom ENGINEER is legally liable. Nothing in this paragraph shall make
the ENGINEER liable for any damages caused by the AUTHORITY or any other contractor
or consultant of the AUTHORITY.
10.2. ENGINEER shall not be liable to AUTHORITY for any special, indirect or consequential
damages, such as, but not limited to, loss of revenue, or loss of anticipated profits.
11. CONTRACTOR INDEMNIFICATION AND CLAIMS.
11.1. AUTHORITY agrees to include in all construction contracts the provisions of Articles 7. 1,
and 7.2, and provisions providing contractor indemnification of AUTHORITY and
ENGINEER for contractor's negligence.
11.2. AUTHORITY shall require construction contractor(s) to name AUTHORITY and
ENGINEER as additional insureds on the contractor's general liability insurance policy.
12. COMPLIANCE WITH LAWS. In performance of the SERVICES, ENGINEER shall comply with
applicable regulatory requirements including federal, state, and local laws, rules, regulations, orders,
codes, criteria and standards. ENGINEER shall procure the permits, certificates, and licenses
necessary to allow ENGINEER to perform the SERVICES. ENGINEER shall not be responsible for
procuring permits, certificates, and licenses required for any construction unless such responsibilities
are specifically assigned to ENGINEER in Attachment B, SCOPE OF SERVICES.
13. INSURANCE.
13.1. During the performance of the SERVICES under this AGREEMENT, ENGINEER shall
maintain the following insurance:
13.1.1. General Liability Insurance with bodily injury limits of not less than
$1,000,000 for each occurrence and not less than $1,000,000 in the aggregate, and with
property damage limits of not less than $100,000 for each occurrence and not less than
$100,000 in the aggregate.
13.1.2. Automobile Liability Insurance with bodily injury limits of not less than
$1,000,000 for each person and not less than $1,000,000 for each accident and with property
damage limits of not less than $100,000 for each accident.
13.1.3. Worker's Compensation Insurance in accordance with statutory requirements and
Employers' Liability Insurance with limits of not less than $100,000 for each occurrence.
13.1.4. Errors and Omissions Insurance to remain in effect during the PROJECT and the
term of any legal liability. Errors and Omissions coverage to be for a minimum of
$1,000,000, deductibles subject to approval.
13.2. ENGINEER shall furnish AUTHORITY certificates of insurance which shall include a
provision that such insurance shall not be canceled without at least 30 days written notice
to the AUTHORITY.
AGREEMENT FOR ENGINEERING- MASTER PLAN
14. OWNERSHIP AND REUSE OF DOCUMENTS.
14.1. All documents, including original drawings, estimates, specifications, field notes and data
shall become and remain the property of the AUTHORITY.
14.2. AUTHORITY'S reuse of such documents without written verification or adaptation
by ENGINEER for the specific purpose intended shall be at AUTHORITY'S risk.
15. TERMINATION OF AGREEMENT.
15.1. The obligation to continue SERVICES under this AGREEMENT may be terminated by
either party upon fifteen days written notice in the event of substantial failure by the other
party to perform in accordance with the terms hereof through no fault of the terminating
party.
15.2. AUTHORITY shall have the right to terminate this AGREEMENT, or suspend performance
thereof, for AUTHORITY'S convenience upon written notice to ENGINEER; and
ENGINEER shall terminate or suspend performance of SERVICES on a schedule
acceptable to AUTHORITY. In the event of termination or suspension for AUTHORITY'S
convenience, AUTHORITY shall pay ENGINEER for all SERVICES performed to the date
of termination in accordance with provisions of Attachment D, COMPENSATION. Upon
restart of a suspended project, ENGINEER's contract price and schedule shall be equitably
adjusted.
16. NOTICE.
Any notice, demand, or request required by or made pursuant to this AGREEMENT shall be deemed
properly made if personally delivered in writing or deposited in the United States mail, postage
prepaid, to the address specified below.
To ENGINEER: Joseph M. Gorgan Greeley
and Hansen LLC
100 S. Wacker Drive, Suite 1400
Chicago, Illinois 60606
To AUTHORITY: Owasso Public Works Authority
P.O. Box 180
Owasso, Oklahoma 74055
Attention: Roger Stevens
16.1. Nothing contained in this Article shall be construed to restrict the transmission of routine
communications between representatives of ENGINEER and AUTHORITY.
17. UNCONTROLLABLE FORCES. Neither AUTHORITY nor ENGINEER shall be considered to be in
default of this AGREEMENT if delays in or failure of performance shall be due to forces which are
beyond the control of the parties; including, but not limited to: fire, flood, earthquakes, storms,
lightning, epidemic, war, riot, civil disturbance, sabotage; inability to procure permits, licenses, or
authorizations from any state, local, or federal agency or person for any of the supplies, materials,
accesses, or services required to be provided by either AUTHORITY or ENGINEER under this
AGREEMENT; strikes, work slowdowns or other labor disturbances, and judicial restraint.
AGREEMENT FOR ENGINEERING - MASTER PLAN
18. SEVERABILITY. If any portion of this AGREEMENT shall be construed by a court of
competent jurisdiction as unenforceable, such portion shall be severed herefrom, and the balance
of this AGREEMENT shall remain in full force and effect.
19. INTEGRATION AND MODIFICATION. This AGREEMENT includes Attachments A, B, C, D, E, F
and represents the entire and integrated AGREEMENT between the parties; and supersedes all prior
negotiations, representations, or agreements pertaining to the SCOPE OF SERVICES herein, either
written or oral. AUTHORITY may make or approve changes within the general Scope of Services in
this AGREEMENT. If such changes affect ENGINEER's cost of or time required for performance of
the services, an equitable adjustment will be made through an amendment to this AGREEMENT.
This AGREEMENT may be amended only by written instrument signed by each of the Parties.
20. DISPUTE RESOLUTION PROCEDURE. In the event of a dispute between the ENGINEER and the
AUTHORITY over the interpretation or application of the terms of this AGREEMENT, the matter
shall be referred to the Director of Public Works for resolution. If the Director of Public Works is
unable to resolve the dispute, the matter may, in the Director's discretion, be referred to the City
Manager for resolution. Regardless of these procedures, neither party shall be precluded from
exercising any rights, privileges or opportunities permitted by law to resolve any dispute.
21. ASSIGNMENT. ENGINEER shall not assign its obligations undertaken pursuant to this
AGREEMENT, provided that nothing contained in this paragraph shall prevent ENGINEER from
employing such independent consultants, associates, and subcontractors as ENGINEER may deem
appropriate to assist ENGINEER in the performance of the SERVICES hereunder.
22. APPROVAL. It is understood and agreed that all work performed under this AGREEMENT shall be
subject to inspection and approval by the Public Works Department of the City of Owasso, and any
plans or specifications not meeting the terms set forth in this AGREEMENT will be replaced or
corrected at the sole expense of the ENGINEER. The ENGINEER will meet with the City staff
initially and periodically thereafter and will be available for public meetings and /or City of Owasso
presentations.
23. KEY PERSONNEL. In performance of the SERVICES hereunder, ENGINEER has designated
Joseph M. Gorgan as Project Manager for the PROJECT. ENGINEER agrees that no change will
be made in the assignment of this position without prior approval of AUTHORITY.
AGREEMENT FOR ENGINEERING - MASTER PLAN
IN WITNESS WHEREOF, the parties have executed this AGREEMENT in multiple copies on the respective
dates herein below reflected to be effective on the date executed by the Chair of the AUTHORITY.
Joseph M. Gorgan
Principal
Ryan M. Christopher
Associate
APPROVED:
Authority Clerk Chair
Date
APPROVED AS TO FORM:
Authority Attorney
AGREEMENT FOR ENGINEERING - MASTER PLAN
Agreement for Engineering Services
Owasso Public Works Authority
Wastewater Master Plan Update - 2014
Attachment A - Scope of Project
SCOPE OF PROTECT. The PROJECT consists of preparing an update to the Owasso Public Works
Authority Wastewater Master Plan, which was last updated in 2005. The execution of the tasks will be
broken up into five tasks as shown below.
1. Project Kick Off
2. Documentation of Needs
3. Master Plan Update Report
a. Document Current Wastewater Situation
b. Future Situation
C. Collection System Model Update
d. Development of Alternatives for Evaluation
e. Evaluation of Alternatives (as needed)
f. Selected Plan
g. Implementation Schedule
4. Progress Meetings
5. ODEQ Coordination
A more detailed description of each work task is provided as part of Attachment B.
ATTACHMENT A- SERVICES A-1
Agreement for Engineering Services
Owasso Public Works Authority
Wastewater Master Plan Update - 2014
Attachment B - Scope of Services
The services to be performed by the ENGINEER, Greeley and Hansen LLC, under this AGREEMENT
will consist of updating the Owasso Public Works Authority 2005 Wastewater Master Plan Update. The
execution of the work will be broken up into twelve major work tasks, as stated below. Further, it is
understood and agreed that the date of beginning, rate of progress, and the time of completion of the work to
be done hereunder are essential provisions of this AGREEMENT; and it is further understood and
agreed that the work embraced in this AGREEMENT shall commence upon execution of this AGREEMENT
and receipt of Notice to Proceed.
Greeley and Hansen LLC proposes to furnish the OWASSO PUBLIC WORKS AUTHORITY the following
professional engineering services for the development of an updated to the Wastewater Master Plan Update
completed in 2005 by Greeley and Hansen. The tasks to complete this work are described below:
A. Project Kick Off
a) Meeting - Greeley and Hansen will conduct a meeting with Public Works staff
personnel to initiate project activities. The purpose of the meeting is to:
i. Identify Key Project Personnel from the City and the Engineering Project Team
ii. Review General Project Requirements and Scope
Review previous Master Plan from 2005 and determine strategies to improve
project.
iv. Discuss role of Oklahoma Department of Environmental Quality during
Master Planning stage.
V. Establish the Appropriate Lines of Communication and Procedures for
Informational Requests and Reviews.
vi. Discuss Project Schedule and Identify Key Project Deliverables.
vii. Establish Meeting Note Protocol.
viii. Submit Initial Information Request to City.
b) Wastewater Treatment Plant (W WTP) Review — Key City and project team members tour the
WWTP following the Kick Off meeting with the objective of assessing plant conditions and
identifying short -term and long -tern improvements.
C) Lift Stations Tour — Key City and project team members tour the lift stations
following the Kick Off meetings with the objective of assessing lift station
conditions and identifying short -term and long term improvements.
d) Meeting and Site Visit Notes — Meeting and site visits notes will be prepared detailing the
key topics discussed and any decisions and observations made during the meeting and at
the site visits.
Deliverable: Draft and final meeting notes will be submitted in PDF format.
7Z
B. Documentation of Needs
a) Gather Data - Discuss with City staff needed improvements to the wastewater collection
system, lift stations and treatment plant. Obtain from City existing reports and other
information regarding those needs.
b) Treatment Plant - Summarize data gathered in relation to the Wastewater Treatment Plant
based upon site visit observations and information provided by the City.
C) Collection System - Summarize data gathered in relation to the collection system based
upon site visit observations and information provided by the City.
d) Receiving Stream — Provide a description of the receiving stream classification.
e) NPDES Permit Requirements — Summarize the treatment plant's current NPDES permit,
which is due to expire in 2017, and assess potential future permit requirements. The latest
TMDL Study will be reviewed and incorporated into the future load limits from the
plant.
Deliverable: A list of items and information required to prepare the Master Plan Update
will be requested.
C. Document Current Wastewater Situation
a) General —The following information will be compiled:
i. Study Area and existing Service Area Maps — The 2005 Master Plan will form the
bassis of the current Study and Service Area. Further information will be
requested from the City of Owasso to determine the extent of changes from the
previous Master Plan. The maps will be incorporated into the Master Plan.
ii. Collection System Map - Information provided will be used to describe Owasso's
existing collection system and the existing collection system map will be
incorporated into the Master Plan.
Current Area Population
iv. Discharge rates of any metered industrial dischargers.
V. Pump station run-time records during dry and wet weather periods.
b) Collection System - Describe the City of Owasso collection system including lift
stations. Evaluate the condition of the existing structures and equipment. Identify number
of pumps and capacities (head and flow) of each lift station. Document arrangements for
standby power. Prepare a bases for design of the existing lift stations. Develop a GIS map
of the City's major sewers and lift stations.
C) Treatment Plant - Evaluate the condition of existing structures and equipment. Describe the
processes and major components of the treatment plant. Prepare a bases of design for the
plant based upon information famished by Owasso staff, taking into account any
improvements that may have been made since the last plant expansion. Develop an updated
plant process schematic diagram and site plan.
d) Flow Rates
i. Historical Flows - Summarize historical plant flow rates, both average and peak,
from monthly reports of operation (MROs) from the past three years.
ii. Infiltration and Inflow - Review MROs for a 7 to 14 day period of dry weather
during seasonal high groundwater. Estimate the peak sustained
B -2
infiltration rate by subtracting the estimated sanitary sewage production rate from
the flow rate during periods of high groundwater period.
e) Wastewater and Biosolids Characteristics - From MROs, summarize existing
wastewater and biosolids characteristics from the past three years.
Deliverable: To be included in Master Plan draft and final.
D. Future Situation
a) Service Area - Develop a GIS map showing the 20 -year service area.
b) Population Projection - Project service area population throughout the 20- year
planning period.
C) Flows - Project wastewater flows throughout the 20 -year planning period.
d) Wastewater and Biosolids Characteristics - Project future wastewater and biosolids
characteristics for the 20 -year planning period, taking into account any major changes in
loadings from Owasso's major customers.
e) Pennit Requirements - Review potential changes in future NPDES permit
requirements.
Deliverable: To be included in Master Plan draft and final.
E. Collection System Model Update
a) hie etjne — Conduct internal project team meeting to review information provided by City
staff, review of the existing model completed as part of the 2005 Master Plan, and review
updates to the collection system since that time.
b) Hydraulic Model Update
Delineate Sewersheds — Update GIS map previously used to delineate the service
areas, or "sewersheds" tributary to each of Owasso's lift stations. Update
sewersheds for lift stations that have been added or removed from the collection
system.
Overlay GIS Census Data — Utilize population data compiled by the US Census
Bureau and information provided by the City of Owasso to assist in calculating the
latest populations in the areas served by each of Owasso's lift stations.
Collection System Survey— Request from the City of Owasso a GPS survey of key
manholes in the service area to determine X, Y and Z coordinates to an accuracy of
=0.01 M. Use the latest record drawings from the city to confirm these locations.
B -3
iv. Evaluate Pump Station Run -Time Records — If available, use detailed flow
monitoring from each of the pumps stations. Pump station flow records will be
utilized in lieu of a detailed flow - monitoring program. The pump run time totals will
be recorded on a regular basis and used to compute daily flow totals. Collected data
will be utilized to evaluate system flows under both dry and wet weather conditions.
This data will also be used in the calibration of the model.
V. Update Model Inflow Rates —The model will be updated almost entirely within the
GIS environment. By overlaying the model nodes, their corresponding sewersheds,
and per capita flow rates developed in the preceding steps; inflow rates will be
updated into the model. The model will simulate wastewater flow, infiltration, and
diurnal flow patterns.
vi. Update Hydraulic Model — Using the City of Owasso's latest GIS Map, the model
will updated to enable storing of input and output in a interactive mapping
environment. This GIS map will be used to assist in communicating model results.
The GIS map will be turned over to the City upon project completion. Using the
selected modeling software, construct a hydraulic model of the major sewers, those
10" and larger. This model will be capable of simulating those hydraulic
phenomena that were found to be required during the model selection process. The
selected model will be capable of simulating both dry and wet weather flows, and
any hydraulic phenomena that may occur within the City's sanitary sewer system.
These phenomena may include open channel flow, pressurized flow, sewer
surcharging, pump stations, direct inflow, and rain induced inflow and infiltration.
vii. Update Hydrologic Model —The selected hydraulic model will be updated to
produce dry and wet weather flows. The model will be capable of simulating
wastewater flows, dry weather infiltration, diurnal flows, and wet weather inflow
and rain induced inflow and infiltration. GIS maps indicating sewershed model
parameters including base flow production, infiltration rates, etc will be produced.
viii. Convert Collection System Model to EPA -SWMM — Convert the selected model
to the EPA -SWMM model.
C) Sewer Capacity Evaluation
Trunk Sewer Capacity Evaluation — Using the updated hydraulic model, the
adequacy of the trunk sewers to convey existing flows will be determined. Any
hydraulic deficiencies will be identified. Since the model will be integrated with the
GIS system database, an interactive GIS map of the trunk sewers identifying
hydraulic deficiencies and the effected areas will be identified.
ii. Ultimate Build -Out - Development information provided by the City will be
incorporated to perform a preliminary sizing and routing of the conveyance
facilities necessary to accommodate the corresponding increase in flows. The
model will be used as the primary tool for simulating increases in flows
B -4
and evaluating the adequacy of proposed system expansion. The expansion of the
model to simulate development will be performed in an integrated GIS environment.
An interactive GIS map of planned development will be developed. This will allow
the hydrologic model to be altered as actual development and system expansion
occur.
Year 2025 — The model will be used to verify the adequacy of required system
improvements required for development projected through the year 2025.
iv. Year 2035 —The model will be used to verify the adequacy of required system
improvements required for development projected through the year 2035.
d) Model Calibration — The model will be calibrated to reproduce base, or dry weather flows.
The City, which owns multiple flow meters, will set up the flow meters at specific points in
the system to measure flow. This data will then be used to calibrate the model.
e)
Summary-- A summary will be prepared that details that changes made to the model, sewer
capacity evaluation, as well as the accuracy of the model calibration.
Deliverable: The results of the model and summary will be included in Master Plan draft
and final. The model will be turned over to the City of Owasso at the completion of the
project.
F. Development of Alternatives for Evaluation
a) Collection Svstem
Gravity sewers — Develop routing and sizing alternatives for trunk sewer capacity
required for the years 2025, 2035 and the ultimate build -out to the fence line.
Lift Stations - Identity locations and capacities for pump stations required to
provide adequate system capacity for the years 2025, 2035, and ultimate build -out.
b) Treatment Plant
Plant Hydraulic Computations and Analysis — Prepare hydraulic computations for the
plant from effluent back to the headworks. Identify deficiencies in hydraulic
capacity and develop alternatives to correct deficiencies as required. Evaluate
hydraulic conditions for current and future flows from the collection system
Liquid Treatment Processes — Develop alternatives for liquid stream processes based
on projected future flows and wastewater characteristics, treatment needs and future
NPDES permit requirements. For each alternative, as needed, describe
L•M
and screen potential alternatives and select the most promising alternatives for
detailed evaluation.
o Water Reuse — 2 -3 alternatives for water reuse from the treatment plant's
effluent flow stream will be evaluated and included in the report.
Biosolids Treatment, Handling Storage and Dis oa sal - Develop alternatives for
biosolids treatment, handling, storage and disposal based on future biosolids
quantities and disposal requirements. For each alternative as needed, describe and
screen potential alternatives and select the most promising alternatives for detailed
evaluation.
Deliverable: To be included in Master Plan draft and final.
G. Evaluation of Alternatives (as needed)
a) Collection System - For each evaluated alternative perform the following:
Capital Costs - Prepare preliminary opinions of probable construction costs for
each alternative.
ii. O. M & R Costs - Prepare preliminary opinions of operation, maintenance and
replacement costs.
Present Worth - Compare the present worth of the alternatives to identify the most
cost - effective alternative.
b) Liquid Treatment — For each evaluated alternative perform the following:
Capital Costs - Prepare preliminary opinions of probable construction costs for
each alternative.
ii. O. M & R Costs - Prepare preliminary opinions of operation, maintenance and
replacement costs.
Present Worth - Compare the present worth of the alternatives to identify the most
cost - effective alternative.
c) Biosolids Treatment - For each evaluated alternative perform the following:
Capital Costs - Prepare preliminary opinions of probable construction costs for
each alternative.
ii. O, M & R Costs - Prepare preliminary opinions of operation, maintenance and
replacement costs.
Present Worth - Compare the present worth of the alternatives to identify the most
cost - effective alternative.
B -6
d) Plant Hydraulic Analysis - For each evaluated alternative perform the following:
Capital Costs - Prepare preliminary opinions of probable construction costs for
each alternative.
O, M & R Costs - Prepare preliminary opinions of operation, maintenance and
replacement costs.
iii. Present Worth - Compare the present worth of the alternatives to identify the most
cost - effective alternative.
Deliverable: To be included in Master Plan draft and final.
H. Selected Plan
a) Treatment Plant - Describe recommended treatment plant improvements. Prepare design
summary (bases of design). Prepare schematic diagram and site plan for upgraded plant.
b) Collection System - Describe recommended collection and lift station system
improvements.
C) Cost Summary - Summarize preliminary opinions of capital costs for the
selected plan.
Deliverable: To be included in Master Plan draft and final.
I. Implementation Schedule
a) Schedule - Develop a schedule of implementation for each phase of the program,
including design, construction and performance certification of the recommended
facilities. Coordinate schedule with implementation schedule of other capital
improvement programs of the City of Owasso.
Deliverable: To be included in Master Plan draft and final
J. Master Plan Update Report
a) Draft Report - Prepare a draft report summarizing the preceding tasks for submission to the
City.
b) Final Report - Incorporate City comments and recommendations into the Final
Report. The Final Report will become the Master Planning document that records
the Capital Improvements Program for use throughout the 20- year planning period.
Deliverable: A draft Master Plan Report will be submitted to the City of Owasso for review.
Two (2) hard copies will be submitted. After incorporating comments from the City, the final
Master Plan Update will be submitted. Two (2) hard copies and a
8 -7
CD ROM with a PDF of the Master Plan, CAD files, and the hydraulic model will be
submitted.
K. Project Progress Meetings
a) Project Progress Meetings - Attend two (2) project progress meetings. Meetings will allow
for input by City staff on the Approach and results of tasks. Prepare meeting notes for
distribution to key project personnel.
Deliverable: Draft and final meeting notes will be submitted in PDF format.
L. ODEQ Coordination
a) ODE- Coordination — Coordinate with ODEQ during the master planning process. Meet in
Oklahoma City to go through the master plan and respond to any questions or comments
that may arise from ODEQ.
Deliverable Draft and final meeting notes with ODEQ will be submitted in PDF format.
L•M.
Agreement for Engineering Services
Owasso Public Works Authority
Wastewater Master Plan Update 2014
Attachment C - Responsibilities of the Authority
RESPONSIBILITIES OF THE AUTHORITY. The AUTHORITY agrees:
A. Reports. Records, etc.- To furnish, as required by the work, and not at expense to the
ENGINEER:
a) Records, reports, studies, plans, drawings, and other data available in the files of the
AUTHORITY that may be useful in the work involved under this AGREEMENT.
b) ENGINEER will reasonably rely upon the accuracy, timeliness, and completeness of the
information provided by AUTHORITY.
B. Access - To provide access to public and private property when required in performance of
ENGINEER's services.
C. Staff Assistance. Designate in writing a person to act as its representative in respect to the work to
be performed under this AGREEMENT, and such person shall have complete authority to transmit
instructions, receive information, interpret and define AUTHORITY'S policies and decisions with
respect to materials, equipment, elements and systems pertinent to the services covered by this
AGREEMENT.
a) Furnish staff assistance in locating, both horizontally and vertically, existing AUTHORITY
owned utilities.
D. Review Examine all studies, reports, sketches, estimates, specifications, drawings, proposals
and other documents presented by ENGINEER and render in writing decisions pertaining thereto
within one month of submittal time so as not to delay the services of ENGINEER.
ATTACHMENT C- REPONSIBILITIES OF CITY C-1
Agreement for Engineering Services
City of Owasso, Oklahoma
Wastewater Master Plan Update 2014
Attachment D - Compensation
The AUTHORITY agrees to pay, as compensation for services set forth in Attachment B, a total lump
sum fee of One hundred eighteen thousand dollars ($118,000.00) for the services described in
Attachment B.
ENGINEER shall submit monthly invoices based upon the proportion of the total services actually
completed at the time of billing. Invoices are due and payable within 30- calendar days of receipt by the
AUTHORITY. A breakdown of the lump sum amount to be billed for each of the work tasks is shown as
follows:
Notes:
1. The amounts shown are estimates for each work task and shall not be considered as an upper limit
for each task.
ATTACHMENT 0- COMPENSATION D-1
Wastewater Master Plan Update 2014
Work Task
FEE(1)
A.
Project Kick Off
--S2,028
B.
Documentation of Needs
$3,516
C.
Document Current Wastewater Situation
$6,009
D.
Future Situation
E.
----$4,173
Collection System Modeling Update
$43,443
F.
Development of Alternatives for Evaluation
$8,739
G.
Evaluation of Alternatives
$10,629
H.
Selected Plan
$6,549
1.
Implementation Schedule
$1,476
J.
Master Plan Update Report
$19,482
K.
Proejct Progress Meetings
$6,090
L.
ODEQ Coordination
$2,910
Subtotal
$115,000
Other Direct Costs (Travel)
$3,000
Total
$118,000
Notes:
1. The amounts shown are estimates for each work task and shall not be considered as an upper limit
for each task.
ATTACHMENT 0- COMPENSATION D-1
City of Owasso, Oklahoma
Public Works Department
Wastewater Master Plan Update 2014
Attachment E - Fee /Manhour Breakdown Summary
Greeley and Hansen LLC
August 2014
Project
Project
GIs/
Project
Word
Master Plan Update Tasks
Director
Manager
Modeler
Engineer
CAD
Processing
Total
1
Project Kick Off
$
-
$
1,008
$
$
1,020
$
-
$ -
$
2,028
2
Documentation of Needs
$
-
$
252
$
$
3,264
$
-
$ -
$
3,516
3
Document Current Situation
$
261
$
756
$
$
4,692
$
300
$ -
$
6,009
4
Future Situation
$
261
$
756
$
$
2,856
$
300
$ -
$
4,173
5
Collection System Model Update
$
261
$
2,268
$
3 3,3 60
$
5,304
$
2,250
$ -
$
43,443
6
Development of Alternatives for Evaluation
$
261
$
504
$
1,920
$
5,304
$
750
$ -
$
8,739
7
Evaluation of Alternatives
$
783
$
504
$
2,880
$
5,712
$
750
$ -
$
10,629
8
Selected Plan
$
783
$
1,260
$
960
$
2,856
$
600
$ -
$
6,459
9
Implementation Schedule
$
-
$
252
$
-
$
1,224
$
-
$ -
$
1,476
10
Master Plan Update Report
$
522
$
1,008
$
3,840
$
4,692
$
2,700
S 6,720
$
19,482
11
Project Progress Meetings
$
522
$
2,016
$
1,920
$
1,632
$
-
$ -
$
6,090
12
ODEQ Coordination
$
522
$
756
$
-
$
1,632
$
-
$ -
$
2,910
Sub - Total, $
$4,176
$11,340
$44,880
$40,188
$7,650
$6,720
$114,954
Other Direct
Costs
Travel
$
3,000
Sub -Total
$
3,000
Project Total
$
118,000
Agreement for Engineering Services
Owasso Public Works Authority Master
Plan Update - 2014
Attachment F — Project Schedule
SCHEDULE: The schedule for the Master Plan Update project will be conducted in a single phase. It is
anticipated that the project will require approximately 10 months to complete. The schedule below
illustrates a start date of November 1, 2014 and an approximate completion date of September 15, 2015.
The schedule is as follows:
• Master Plan Update Kick Off Meeting — November 1, 2014
• Owasso to begin Flow Monitoring for Model Calibration (3 Months) — December I — February 31,
2014
• Master Plan Update Draft Due —July 1, 2015
• Receive Comments from City Staff— August 1, 2015
• Submit Final Master Plan Update — September 1, 2015
ATTACHMENT P- SCHEDULE F-1