HomeMy WebLinkAbout2013.11.05_96 and 129 infrastructure_SAMsPROJECT COMPLETION REPORT
PROJECT: E 96 St North and N 129 E Avenue Infrastructure Improvements (SAM'S
DATE PROJECT WAS INITIATED: April 17, 2012
DATE PROJECT WAS COMPLETED: November 5 2013
DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department
STAFF COMMENTS: The proiect consisted of widening E 96 St N to N 136 E
Ave, N 129 E Ave to the ODOT frontage road• and the ODOT frontage road from N 129
E Ave to E 99 St N. In addition 8 "sanitary sewer was extended 627' from the southeast
corner of the CVS building and then north to the site Lastly, a 16 -inch water main was
extended 1.2 miles from E 96 St N and Garnett Road to the development site On April
17, 2012, the City Council awarded a development agreement with SAM's As part of the
agreement, SAM's would initially pay all cost incurred for the design and construction of
the public improvements Furthermore Sam's will contribute $500,000 towards the
actual costs. In return, reimbursement to SAM's will be made from sales tax revenue
generated from this site to include Sam's Club and any future businesses located on any
of the out lots. In January 2013 construction commenced with completion in November
2013. Five change orders were issued through the duration of the project in the amount of
$301,414 to reflect actual quantities provided Final construction cost for the project was
$5,535,929. With the Sam's contribution of $500,0K the actual reimbursement to Sam's
will be $5,035,929
Roger Stevens
PROJECT COORDINATOR
App, ued this 28th day of July, 2014