HomeMy WebLinkAbout2015.02.17_fy 14 street rehabiltation programPROJECT COMPLETION REPORT
PROJECT: Street Rehabilitation Program (FY 2013 -2014
DATE PROJECT WAS INITIATED:_ August 20, 2013
DATE PROJECT WAS COMPLETED: February 17, 2015
STAFF COMMENTS: Included in FY 2013 -2014 Budget, the Capital Improvements
Fund allowed for the expenditure of $1,020,000 for the repair and /or resurfacing
of residential and non - residential roadways throughout the city.
Phase I of the rehabilitation program included preventive maintenance such as
crack sealing on various road segments in various locations. This work was
performed by Keystone Services in the amount of $29,384.04.
Phase II of the program included fog seal, pavement repair, as well as concrete
curb and gutter replacement. This work was performed by a Tri -Star Construction
in the amount of $760,652.15, an underrun of $66,643.85.
Phase III of the program included the paving and /or surfacing of approximately
2.5 lane -miles of roadway surface. Tulsa County provided the use of County
labor and equipment for the paving and /or resurfacing and the City purchased
the necessary materials such as asphalt, traffic signage for traffic control and
required striping. The cost for asphalt, tac oil and other materials and services
totaled $102,584.51.
Final construction cost for this project was $892,620.70
this 21St day of July, 2015
Chair