HomeMy WebLinkAbout2018.04_City Radio System UpgradePROJECT COMPLETION REPORT PROJECT: City Radio System Upgrade DATE PROJECT WAS INITIATED: October 5, 2015 DATE PROJECT WAS COMPLETED: April 2018 STAFF COMMENTS: Included in FY 2015/16 Budget the Capital Improvements Fund allowed for the expenditure of $ 2.968 762 02 for a P -25 Upgrade to the City Radio System. This upgrade of radio equipment to Project 25 standards included replacement of all tower -based eauipment base stations routers switches controllers and transmission lines. At the Dispatch facility the upgrade included replacement of all the console workstations along with associated microphones and speakers The uparade also included the replacement of all mobile and handheld subscriber units totaling approximately 365 radios On October 5 2015 the purchase of the P -25 Radio system Upgrade was authorized The order with the manufacturer was placed and the equipment was placed into the manufacturer's production schedule The staging of the eauipment commenced July 2016. Installation of the subscriber units was started October 2016. System compliance began January 2017 with final testing and acceptance March 2017. System documentation and close out documents were received August 2018. Final cost for this project was $ 2,968,762.02. Approved by the Sales Tax Watchdog committee September 24*Jl 2018 M. Stev ns; ity Clerk