HomeMy WebLinkAbout2018.12.04_E 76 Street North and Main Street Intersection Improvement ProjectPROJECT COMPLETION REPORT
PROJECT: East 76 Street North and Main Street Intersection Improvements
(Phase 1 -II)
DATE PROJECT WAS INITIATED: March 21, 2017
DATE PROJECT WAS COMPLETED: December 4, 2018
PROJECT DETAILS: The improvements were separated into two phases.
First phase improvements included construction of a fifth lane to the south
side of East 76th Street North allowing for a protected left -turn lane; a
complete reconstruction of the intersection from asphalt to concrete
new traffic signals and hardware, stamped brick crosswalks landscaping
and new underground public infrastructure. In March 2017 City Council
awarded Phase I improvements to Grade Line Construction in the amount
of $1,807,617.29. Construction was completed, realizing an under run of
$17,943.98, for a revised contract amount of $1,789,673.31 *
Phase II improvements included installation of streetlights irrigation
landscape and sidewalk which coincided with the completion of
Seven6Main Commercial Development. In August 2018 City Council
awarded Phase II to Grade Line Construction in amount of $117,671. In
December 2018, City Council approved final pay in amount of $24,648.31,
realizing an under run of $19,410.70, for a revised contract amount of
98,260.30. In addition, Phase II Improvements had a separate contract to
install electrical outlets on the existing streetlights along Main Street from
76th to 3rd Street. In February 2019, City staff approved a contract with
EMC Electrical Mechanical in the amount of $24,500. As a result, total cost
for Phase. I and Phase II Improvements are $1912433.61 Capital
Improvements funded $1,060,586.76 with the remaining balance funded
from Vision 2025 and Owasso Public Works Authority.
Roger Stevens, Public Works Director
Approved by the Sales Tax Oversight Committee
March 25, 20
uliann M. Steyv ns, City Clerk