HomeMy WebLinkAbout2018.12.04_E 76 Street North and Main Street Intersection Improvement ProjectPROJECT COMPLETION REPORT PROJECT: East 76 Street North and Main Street Intersection Improvements (Phase 1 -II) DATE PROJECT WAS INITIATED: March 21, 2017 DATE PROJECT WAS COMPLETED: December 4, 2018 PROJECT DETAILS: The improvements were separated into two phases. First phase improvements included construction of a fifth lane to the south side of East 76th Street North allowing for a protected left -turn lane; a complete reconstruction of the intersection from asphalt to concrete new traffic signals and hardware, stamped brick crosswalks landscaping and new underground public infrastructure. In March 2017 City Council awarded Phase I improvements to Grade Line Construction in the amount of $1,807,617.29. Construction was completed, realizing an under run of $17,943.98, for a revised contract amount of $1,789,673.31 * Phase II improvements included installation of streetlights irrigation landscape and sidewalk which coincided with the completion of Seven6Main Commercial Development. In August 2018 City Council awarded Phase II to Grade Line Construction in amount of $117,671. In December 2018, City Council approved final pay in amount of $24,648.31, realizing an under run of $19,410.70, for a revised contract amount of 98,260.30. In addition, Phase II Improvements had a separate contract to install electrical outlets on the existing streetlights along Main Street from 76th to 3rd Street. In February 2019, City staff approved a contract with EMC Electrical Mechanical in the amount of $24,500. As a result, total cost for Phase. I and Phase II Improvements are $1912433.61 Capital Improvements funded $1,060,586.76 with the remaining balance funded from Vision 2025 and Owasso Public Works Authority. Roger Stevens, Public Works Director Approved by the Sales Tax Oversight Committee March 25, 20 uliann M. Steyv ns, City Clerk