OWASSO PUBLIC WORKS AUTHORITY OCTOBER 15, 1991
On Tuesday, October 15, 1991 the Owasso Public Works Authority met
in a regular session in the Council Chambers at the Community
Center per the Notice of Public Meeting and Agenda posted on the
City Hall bulletin board at 4:00 p.m. on Friday, October 11, 1991.
ITEM 1: CALL TO ORDER.
The meeting was called to order at 7:16 p.m. with Chairman Phillips
presiding.
ITEM 2: FLAG SALUTE.
The flag salute was held during the City Council meeting preceding
this meeting.
ITEM 3: ROLL CALL.
PRESENT: John Phillips, Chairman
Patricia Marlar, Vice Chairman
Mark Thompson, Trustee
Bob Randolph, Trustee
Jason Gittelman, Trustee
Rodney J. Ray, City Manager
Ronald D. Cates, O.P.W.A. Attorney
Jane Buchanan, Secretary
ABSENT: None
A quorum was declared present.
ITEM 4: REQUEST APPROVAL OF THE MINUTES FROM THE OCTOBER 1 1991
MEETING.
A motion was made by M. Thompson, seconded by P.Marlar, to approve
the minutes as written, by reference hereto.
AYE: Thompson, Marlar, Randolph, Gittelman, Phillips
NAY: None
MOTION: Carried 5-0
1
OWASSO PUBLIC WORKS AUTHORITY
OCTOBER 15, 1991
ITEM 5: REQUEST APPROVAL OF THE CLAIMS. M0
A motion was made by P. Marlar, seconded by M. Thompson, to approve
the claims as follows: (1) $24,168.90 and (2) Payroll $17,884.45.
AYE: Marlar, Thompson, Randolph, Gittelman, Phillips
NAY: None
MOTION: Carried 5-0
ITEM 6: REQUEST TRUSTEE APPROVAL AND AWARD OF CONTRACT IN THE
AMOUNT OF $5,185.49 TO KATADYN SYSTEMS INC. FOR THE
PURCHASE OF 168 "ULTRAVIOLET DISINFECTION REPLACEMENT
LAMPS" TO BE USED AT THE WASTEWATER TREATMENT PLANT. BID
OPENING WAS HELD ON OCTOBER 2, 1991.
Mr. Nicholson stated bids were opened and two bids were received:
(1) Katadyn Systems, Inc. $5,185.49 and (2) Trojan Technologies,
Inc. $5, 679.00. Both bids met specifications and he recommended
awarding the bid to the lowest bidder, Katadyn Systems, Inc.
A motion was made by P. Marlar, seconded by M. Thompson, to award
the contract to Katadyn Systems, Inc. in the amount of $5,185.49.
AYE: Marlar, Thompson, Randolph, Gittelman, Phillips
NAY: None
MOTION: Carried 5-0
ITEM 7: REQUEST TRUSTEE APPROVAL AND AWARD OF CONTRACT IN THE
AMOUNT OF $8,519.05 TO WATER PRODUCTS OF OKLAHOMA INC
FOR THE PURCHASE OF WATER SET AND MATERIALS IN BULK
QUANTITY FOR USE IN THE WATER DEPARTMENT. BID OPENING WAS
HELD ON OCTOBER 9, 1991.
Mr. Nicholson stated three bids were received : (1) Utility Supply
Company $9,186.70, (2) Arkansas Meter & Supply Company $9,138.75,
and (3) Water Products of Oklahoma $8,519.05. All bids met
specifications and he recommended awarding the contract to the
lowest bidder, Water Products of Oklahoma, Inc. in the amount of
$8, 519.05.
A motion was made by M. Thompson, seconded by B. Randolph, to award
the contract to Water Products of Oklahoma, Inc. in the amount of
$8,519.05.
AYE: Thompson, Randolph, Marlar, Gittelman, Phillips
NAY: None
MOTION: Carried 5-0
2
OWASSO PUBLIC WORKS AUTHORITY
OCTOBER 15, 1991
ITEM 8: REQUEST TRUSTEE APPROVAL AND AWARD OF CONTRACT IN THE
AMOUNT OF $4,750.00 TO MISER ASPHALT COMPANY FOR THE
PURPOSE OF CONSTRUCTING AN ASPHALTIC CONCRETE PARKING LOT
AND WORK AREA FOR THE OWASSO WATER DEPARTMENT.
Mr. Ray presented this item stating at the last meeting all initial
bids were rejected and the project was to be rebid using "downsized
specifications". The specifications were redesigned and quotes
were solicited from the contractors.
He continued by stating he met with Mr. Randy Miser to negotiate a
final price for the project. Mr. Miser agreed to lay the asphalt
in two "lifts" of two inches each, to lay the second "lift" within
twenty-four hours of the first, and to provide type "B" asphalt
rather than type "C". While this is not the lowest bid, Mr. Ray
stated the staff used a set criteria to review all proposals and
the consensus was this is the "best" bid. This proposal is only
five percent higher ($240.00) than the lowest proposal.
He recommended awarding the contract to Miser Asphalt in the amount
of $4,750.00.
After discussion by the Trustees, a motion was made by M. Thompson,
seconded by B. Randolph, to award the contract to Miser Asphalt
Company in the amount of $4,750.00 as recommended.
AYE: Thompson, Randolph, Gittelman, Marlar, Phillips
NAY: None
MOTION: Carried 5-0
ITEM 9: REPORT FROM O.P.W.A. MANAGER.
None
ITEM 10: REPORT FROM O.P.W.A. ATTORNEY.
None
ITEM 11: UNFINISHED BUSINESS.
None
ITEM 12: NEW BUSINESS.
None
�11
OWASSO PUBLIC WORKS AUTHORITY OCTOBER 15, 1991
ITEM 13• ADJOURN.
With there being no further business to be brought before the
Trustees, a motion was made by M. Thompson, seconded by B.
Randolph, to adjourn.
AYE: Thompson, Randolph, Gittelman, Marlar, Phillips
NAY: None
MOTION: Carried 5-0
Meeting was adjourned at 7:23 p.m.