Loading...
HomeMy WebLinkAbout1999.01.11_Restroom 1 Owasso Sports ParkPROJECT COMPLETION REPORT PROJECT: Restroom #1 at Owasso Sports Park DATE PROJECT WAS INITIATED: May 1997 DATE INITIALLY SCHEDULED FOR COMPLETION: April 16, 1998 DATE ACTUALLY COMPLETED: Final Inspection Held on May 1, 1998 DEPARTMENT RESPONSIBLE FOR PROJECT: STAFF COMMENTS: The restroom was originally put out to bid in June 1997, with only one bid being received in the amount of $91,493. The City Council rejected that bid and authorized the staff to rebid the project. The project was rebid in September 1997. The contract was awarded to Pettijohn Construction in the amount of $85,405. Due to change orders, the final contract amount was $84.070. The City Council accepted the project in May 1998. Funding was included in the Fy 1997 -98 Capital hnprovements Fund. David Warren PROJECT COORDINATOR Parks DEPARTMENT PROJECT MANAGER /- //- 9'--7 DATE