HomeMy WebLinkAbout1999.01.11_Restroom 1 Owasso Sports ParkPROJECT COMPLETION REPORT
PROJECT: Restroom #1 at Owasso Sports Park
DATE PROJECT WAS INITIATED: May 1997
DATE INITIALLY SCHEDULED FOR COMPLETION: April 16, 1998
DATE ACTUALLY COMPLETED: Final Inspection Held on May 1, 1998
DEPARTMENT RESPONSIBLE FOR PROJECT:
STAFF COMMENTS:
The restroom was originally put out to bid in June 1997, with only one bid being received in the
amount of $91,493. The City Council rejected that bid and authorized the staff to rebid the project.
The project was rebid in September 1997. The contract was awarded to Pettijohn Construction in
the amount of $85,405. Due to change orders, the final contract amount was $84.070. The City
Council accepted the project in May 1998. Funding was included in the Fy 1997 -98 Capital
hnprovements Fund.
David Warren
PROJECT COORDINATOR
Parks
DEPARTMENT
PROJECT MANAGER
/- //- 9'--7
DATE