HomeMy WebLinkAbout1996.11.05_Parking Lot City Hall_Community CenterPROJECT COMPLETION REPORT PROJECT: Parking Lot for City Hall / Community Center DATE PROJECT WAS INITIATED: July 11, 1996 DATE INITIALLY SCHEDULED FOR COMPLETION: October 16 1996 DATE ACTUALLY COMPLETED: Accepted November 5. 1996 DEPARTMENT RESPONSIBLE FOR PROJECT: Community Development STAFF COMMENTS: This Project was designed to repair damage to portions of the base of the City Hall / Community Center parking lot and overlay the entire .parking lot with two inches of asphalt The project was completed under a contract between the City of Owasso and APAC - Oklahoma of Tulsa The total contract cost of the project was $24,982. The Capital Improvements Budget included only $12.650 for the project. The City Council authorized the expenditure of an amount not to exceed $12.982 from the General Fund Budget to supplement the Capital Improvement David Warren PROJECT COORDINATOR Community Development January 9. 1997 DATE