Loading...
HomeMy WebLinkAbout1997.04.19_Sports Park Phase IIPROJECT COMPLETION REPORT PROJECT: Sports Park Phase III DATE PROJECT WAS INITIATED: August 1, 1993 DATE INITIALLY SCHEDULED FOR COMPLETION: May 1, 1994 DATE ACTUALLY COMPLETED: April 19, 1994 DEPARTMENT RESPONSIBLE FOR PROJECT: Community Development STAFF COMMENTS: Project consisted of preliminary "dirt work" and rading for four softball fields: installation of lighting for two of those fields: and paving of entrance road. Grading Contract - $32.450 Lighting Contract - $67,500 Paving Contract - $32.012 Total Expenditure - $131,962 Total Appropriated - $132,000 Steve Compton PROJECT COORDINATOR Community Development DEPARTMENT Rodney J Ray CITY MANAGER July 6. 1994 DATE