HomeMy WebLinkAbout2019.04.02_Project Completion Report_Hwy 169 & W Service Rd_N 135 E Ave Service Road ImprovementsPROJECT COMPLETION REPORT
PROJECT: HWY 169 East and West Service Road - North 135th East Avenue Service
Road Improvements
DATE PROJECT WAS INITIATED: February 7, 2017
DATE PROJECT WAS COMPLETED: April 2, 2019
STAFF COMMENTS:
The proiect consisted of constructina a new 3 -lane arterial roadway which extends from
East 106th Street North to East 116th Street North on the west side of US HWY 169 In
February 2017. the City Council awarded an engineering agreement in the amount of
$187,500 to Craft Tull Sparks The engineering design was completed in September 2017
In December 2017. the City Council awarded the construction contract to Grade Line
Construction in the amount of $2,480,078.45. On April 2 2019 the City Council accepted
the completed project for a total contract price of $2.306,903.75, resulting in an underrun
of $173,174.70
Total proiect costs including right -of -way acauisition utility relocations enaineering
design fees, and construction was $2,627,499.00.
Roger Stevens, Public Works Director