Project Status Summary Report
Progress Report #1 Dated June 30, 2017
Owasso Cost Expended
Project Election Estimate Project to Date Design Bid Construction
96 Street from 119 to 129 4/5/2016 $ 5,600,000 $ 39,459 NI 116 Street from 129 to HWY 169 4/5/2016 5,300,000 7,334
116 Street from Garnett to 129 4/5/2016 10,500,000 171,945
116 Street from Mingo to Garnett 4/5/2016 10,500,000 178,907
Total $ 31,900,000 $ 397,645
Legend:
In Progress
Complete
Not Applicable
Completed;
pending ODOT
audit and final
invoicing