HomeMy WebLinkAbout2014.08_ E 106th St N and Garnett Rd Intersection ImprovementsPROJECT COMPLETION REPORT PROJECT: East 106th Street North and Garnett Road Intersection Improvements DATE PROJECT WAS INITIATED: March 2013 DATE PROJECT WAS COMPLETED: August 2014 DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department STAFF COMMENTS: The East 106th Street North and Garnett Road Intersection project consists of roadway widening of the intersection and installation of traffic signals. In April 2013, the Oklahoma Department of Transportation (ODOT) awarded a contract to Paraqon Construction in the amount of $1,952,952.00 - ODOT funded $1,415,834.57 towards the costs of construction. The City contributed $1,741,720.40 which included engineering design, utility relocation, right -away and 20% of the construction cost. Approved by the Sales Tax Watchdog committee September 24, 2018. } ,aI1' UGA/ 4 DUI ; � �m! "Aliann M. Steve s, City Clerk