HomeMy WebLinkAbout2006.12.05_Silver Creek DrainagePROJECT COMPLETION REPORT r�! PROJECT: Silver Creek Drainage DATE PROJECT WAS INITIATED: December 20, 2005 DATE PROJECT WAS COMPLETED: December 5, 2006 DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department STAFF COMMENTS: On December 20, 2005, City Council approved the first of two contracts, a Development Agreement (for $600,000) between the City of Owasso and Tracy Construction Incorporated for the purchase of property and construction of "on- site" facilities. On January 10, 2006, the second contract was approved with Keystone Services, Inc., Oklahoma, for the construction of "off- site" Silver Creek Drainage Improvements in the total amount of $569,229.95. The "on- site" improvements included excavation and grading of detention pond, complete with outlet structure and associated piping, as well as a structure to convey the flow from the Nottingham subdivision to the new detention facility. The "off- site" improvements included stormwater piping improvements throughout the Bradfords and Willows subdivisions, a collection structure in Nottingham, as well as the improvements to the existing Village of Silver Creek detention facility. On -site and Off -site improvements were completed in June 2006 and c) December 2006, respectively. Quantity adiustments at the end of the project resulted in an additional expenditure of $13,748.22. Such were necessary for the installation of additional pipe and structure revisions required to address unanticipated site conditions. Final payment was made for $1,182,978.17, resulting in an expenditure of $832,578.17 from the Capital Improvements Fund. Ana C. Stagg, P.E. PROJECT COORDINATOR Public Works DEPARTMENT PROJECT •O'D t January 10, 2007 DATE Approved this 22nd da of January, 2007. Br da Snow, Chairman