HomeMy WebLinkAbout44_Progress Report_Third-Penny_CIPSALES TAX PROJECTS WATCHDOG COMMITTEE PROGRESS REPORT FY 2004 -2005 CAPITAL IMPROVEMENTS FUND PROJECTS Progress Report #44 Dated 06/30/05 PROJECT Cost Estimate Expended Design Bid Construction Computerization 624,481 614,489 Fire Station Remodel 200,000 183,939 New Fire Station 1,200,000 400 Storm Siren System 234,083 234,083 86 & Mingo Intersection 1,500,000 236,466 86 Street Widening 3,302,000 2,952,099 96 & 129 E Ave Intersection 1,744,000 1,274,208 96 & Hwy 169 Interchange 1,500,000 1,176,552 129 E Ave Widening (Engr only) 360,000 339,498 96 Str Widening (Garnett to Owasso Mkt) 5,400,000 3,121,501 Garnett Widening (86 to 96) 5,400,000 1,875,191 Sports Park Expansion 2,000,000 1,722,998 YMCA Pool 1,000,000 0 Water System Project Engineering 370,403 370,403 X X X X X X X X X X N N X X X X X X X X X _. N N Total $ 24,834,967 $ 14,101,827 Legend: In Progres - Complete -NOt Applicable