HomeMy WebLinkAbout2021.03.22_Street Rehabilitation Program FY 2019PROJECT COMPLETION REPORT PROJECT: Street Rehabilitation Program (FY 2019) DATE PROJECT WAS INITIATED: November 2018 DATE PROJECT WAS COMPLETED: July 2020 STAFF COMMENTS: The 2019 program included pavement repair, as well as concrete curb and gutter replacement, and asphalt overlay in the Original Town, Ator Heights, Lakeridge, Double Oaks and Country Estates III subdivisions. In July 2019, City Council approved a construction contract with Gradeline Construction, LLC, in the amount of $2,123.846.25. In July 2020, the contractor completed the work with a final contract amount of $1,988,350.79, a contract underrun of $135,495.46. In addition to work mentioned above, the project was funded from the Capital Improvements Fund and Street Division 39 -Fund. The Capital Improvements Fund funded $1,204,117 of the total project cost with remainder being funded by the Streets Division 39 -Fund. Roger Stevens, Public Works Director App d this 22n y of March, 2021. Steve Mowery, Chair