HomeMy WebLinkAbout2022.03.28_Project Completion Report_FY 2020 Streeet Rehab ProgramPROJECT COMPLETION REPORT
PROJECT: Street Rehabilitation Program (FY 2020)
DATE PROJECT WAS INITIATED: September 2020
DATE PROJECT WAS COMPLETED: May 2021
STAFF COMMENTS:
The 2020 program included pavement repair, as well as concrete curb and
gutter replacement, and asphalt overlay in the following subdivisions:
• Reconstruction of Dogwood Street and Elm Street between East 8th Street
and East 86th Street North
• Rehabilitation of several streets within Three Lakes II and Three Lakes III
subdivisions
• Rehabilitation of East 861h Place North in Ram Plaza
• Rehabilitation of East 85th Street North and North 128th East Avenue in Elm
Creek Commercial
In September 2020, the City Council approved a construction contract with
Grade Line Construction, LLC, in the amount of $1,534,161.27. In January 2021,
the City Council approved Change Order No. 1, in the amount of $125,000.00,
adding two street segments to the project:
• Mill and Overlay of East 11 th Street between Main Street and Cedar Street
• Construction of a concrete cul -de -sac at the north end of Carlsbad in
Original Town
On March 18, 2021, the City Council accepted the completed project and
authorized final payment to the contractor. The project was funded using
$974,785.00 from the Capital Improvements Fund and the remainder from the
Street Division 39 -Fund.
Roger Stevens, Public Works Director