HomeMy WebLinkAbout2022.09.26_Project Completion Report_South Sports Park Regional Detention Pond ProjectPROJECT COMPLETION REPORT
(Capital Improvements Fund and Other Funds)
PROJECT: South Sports Park Regional Detention Pond Project
DATE PROJECT WAS INITIATED: July 2015
DATE PROJECT WAS COMPLETED: March 2022
STAFF COMMENTS:
In July 2015, the City Council approved an engineering agreement with Meshek and
Associates to design the stormwater regional detention facility and mitigation.
In November 2019, City Council approved a construction contract with Cherokee
Builders, Inc., of Tulsa, Oklahoma. The improvements include a new stormwater detention
pond at the southwest corner of the sports park. The mitigation project accommodates
the wetlands, ponds, jurisdictional stream channel and trees that are displaced by the
proposed detention facility.
On August 17, 2021, the City Council authorized final payment to the construction
contractor and accepted the completed project.
Total project costs of engineering and construction expended from the Capital
Improvements Fund was $3,638,828.00.
Roger Stevens, Public Works Director
Accepted by the Sales Tax Oversight Committee
this ^ day of September, 2022. ^t
Juli n M`Stevens, Cl f Clerk J