HomeMy WebLinkAbout2022.09.26_Project Completion Report_E 106 St N and N 145 E Ave Intersection ImprovementsPROJECT COMPLETION REPORT
(Capital Improvements Fund)
PROJECT: East 106t1 Street North and North 145th East Avenue Intersection
Improvements
DATE PROJECT WAS INITIATED: January 2016
DATE PROJECT WAS COMPLETED: May 2021
STAFF COMMENTS:
In January 2016, the City Council approved an agreement for Engineering Services with
Poe and Associates of Tulsa, Oklahoma for the design of a four -lane intersection with
center turn lanes and right turn lanes where needed. In addition, traffic signals and
sidewalks were part of the design as well.
In August 2020, City Council approved a construction contract with Diversified Civil
Contractors, LLC to expand the intersection and install storm drainage and relocate
water system infrastructure.
On November 2, 2021, the City Council authorized final payment to the construction
contractor and accepted the completed project.
Total project costs of design, engineering, right -of- way /easement acquisition, utility
relocation, and construction was $3,810,827.00.
Roger Stevens, Public Works Director
Accepted by the Sales Tax Oversight Committee
this 26th day of September, 2022.