HomeMy WebLinkAbout08_Progress Report_Vision for OwassoElection Project 4/5/2016 96 Street from 119 to 129 4/5/2016 116 Street from 129 to HWY 169 4/5/2016 116 Street from Garnett to 129 4/5/2016 116 Street from Mingo to Garnett 4/5/2016 116 /Garnett Intersection Improvement Total City of Owasso 551100 Sales Tax Vision For Owasso Fund Progress Report #8 Dated 6 -30 -21 Owasso Cost Expended Estimate Project to Date $ 5,600,000 $ 1,055,667 5,266,098 5,266,098 10,000,000 1,918,759 10,500,000 1,239,204 4,500,000 1,681,643 $35,866,098 $ 11,161,371 `a�aO��pKC!t..,,�o� O U EA.(_, Utility Design ROW Relocation Bid Construction Legend: I -In Progress X - Complete N -Not Applicable P Completed; pending ODOT audit and final invoicing