PROJECT: East 7691 Street Widening (from HWY 169 to North 129th East Avenue)
DATE PROJECT WAS INITIATED: July 2010
DATE PROJECT WAS COMPLETED: December 2022
STAFF COMMENTS:
On May 7, 2013, the City Council approved an agreement for Engineering Services
through Oklahoma Department of Transportation with Poe & Associates, Incorporated of
Tulsa, Oklahoma for the design of a 4 -lane roadway section including 2 -lanes in each
direction with a turn lane to expedite turning movements into the various subdivisions
along the roadway, Additionally, the roadway improvements will include boulevards,
bike lanes; sidewalks, and stormwater drainage improvements.
On December 2, 2019, Oklahoma Department of Transportation approved a
construction contract with Crossland Heavy Construction.
In July 20, 2021, Oklahoma Department of Transportation authorized final payment to the
construction contractor and accepted the completed project. In December 2022,
Federal Highway Administration completed their audit.
Total project costs of design, engineering, right -of- way /easement acquisition, utility
relocation, and construction was $10,058,047.65.
Additional funding was used for this project:
CIP Fund: $4,575,847.65
Federal Grant: $5,482.00.00
Accepted by the Sales Tax Oversight Committee
this 25th day of September, 2023.
Clerk