HomeMy WebLinkAbout2023.09.25_Project Completion Report_East 116th Street North and Garnett Intersection ImprovementsPROJECT COMPLETION REPORT PROJECT: East 116th Street North and Garnett Intersection Improvements DATE PROJECT WAS INITIATED: January 2017 DATE PROJECT WAS COMPLETED: December 2022 STAFF COMMENTS: On January 3, 2017, the City Council approved an agreement for Engineering Services with Guy Engineering of Tulsa, Oklahoma for the design of a four -lane intersection with center turn lanes and right turn lanes where needed. In addition, traffic signals and sidewalks were part of the design as well. On November 16, 2021, City Council approved a construction contract in'the amount of $4,284,397.50 with Crossland Heavy Construction to expand the intersection and install storm drainage and relocate water system infrastructure. On December 20, 2022, the City Council authorized final payment to the construction contractor and accepted the completed project for a total contract amount of $4,030,882.88. Total project costs of design, engineering, right -of- way /easement acquisition, utility relocation, and construction was $5,787,492.00. Additional funding was used to complete this project: ARPA Fund: $4,104,326.00 Vision Recapture: $1,683,166.00 Accepted by the Sales Tax Oversight Committee N 25 '^ day of September, 2023. Jul1 nn M. Stevens, City Clerk