HomeMy WebLinkAbout2025.03.24_East 116 Street Widening_Mingo Road to Garnett RoadPROJECT COMPLETION REPORT
(Sales Tax Vision Funds & General Funds)
PROJECT: East 1161h Street Widening (from Mingo Road to Garnett Road)
DATE PROJECT WAS INITIATED: December 2016
DATE PROJECT WAS COMPLETED: January2025
STAFF COMMENTS:
On December 6, 2016, the City Council approved an agreement for Engineering Services
through the Oklahoma Department of Transportation with Garver, LLC Engineering
Design for the design of a 4-lane roadway section including 2-lanes in each direction
with a turn lane to expedite turning movements into the various subdivisions along the
roadway, Additionally, the roadway improvements will include boulevards, bike lanes,
sidewalks, and stormwater drainage improvements.
On February 21, 2023, City Council awarded a construction contract with Crossland
Heavy Construction.
On January 6, 2025, City Council approved final payment to the construction contractor
and accepted the completed project.
Total project costs for design, engineering, right-of-way/easement acquisition, utility
relocation, and construction was $19,536,201.00 The Sales Tax Vision Fund allocated
$18,034,098.00 and the remaining $1,502,103.00 was funded by the General Fund.
Roger Stevens, Public Works Director
Accepted by the Sales Tax Oversight Committee
t ' 41h day of March, 20�5.
6Ca
Juliann M. Stevens, City Clerk