HomeMy WebLinkAbout2025.09.22_Project Completion Report_Street Rehabilitation Program2025PROJECT COMPLETION REPORT
PROJECT: Street Rehabilitation Program (FY 2022)
DATE PROJECT WAS INITIATED: July 2021
DATE PROJECT WAS COMPLETED: June 2025
STAFF COMMENTS:
The 2022 program included pavement repair, as well as concrete curb and
gutter replacement, and asphalt overlay in the following subdivisions:
• Reconstruction of Baptist Village inner roads
• Rehabilitation of several streets within Three Lakes and Elm Creek
• Rehabilitation of East 103rd Street North collector through Coffee Creek
• Rehabilitation of Mingo Road from East 96th Street North to East 116'h Street
North and East 76th Street North from North 129th East Avenue to North
145th East Avenue (Tulsa County provided labor and equipment).
In August 2022, the City Council approved a construction contract with
Stronghand, LLC, in the amount of $1,618,255.97. In August 2023, the City
Council accepted the completed project for a final contract amount of
$1,472,658.51, a contract underrun of $145,627.46.
The remaining $695,800.49 funded the asphalt materials and roadway striping
related to Mingo Road and East 76th Street North improvements.
Funding Breakdown
CIP Fund: $1,085,404
Other: $1,083,055
Roger Stevens, Public Works Director
Accepted by the Sales Tax Oversight
eAmmittee this 22nd day of September, 2025_
M. Stevens,