HomeMy WebLinkAbout2025.09.22_Project Completion Report_Street Rehabilitation Program2024PROJECT COMPLETION REPORT
PROJECT: Street Rehabilitation Program (FY 2024)
DATE PROJECT WAS INITIATED: July 2023
DATE PROJECT WAS COMPLETED: June 2025
STAFF COMMENTS:
The 2024 program was divided into two phases. The first phase included
pavement repair, as well as concrete curb and gutter replacement, and asphalt
overlay. The second phase included asphalt rejuvenation using High Density
Mineral Bond (HA5).
Below are the following locations:
• East Both Street North from the service road to North 123rd East Avenue
• East 78th Street North and East 79th Court North between North 122nd East
Avenue and North 121It East Avenue
• North 121It East Avenue between East 79th Court North and East 78th Street
North
• Crescent Ridge
• Burberry Place
• Keys Landing
• Hickory Creek
Phase 1 - In October 2024, the City Council approved a construction contract
with Grade Line Construction, LLC for $1,790,862.30. On June 3, 2025, the City
Council accepted the completed project for a final contract amount of
$1,711,510.00, a contract underrun of $79,352.30.
Phase 2 - In June 2024, the City Council approved a construction contract with
Holbrook Asphalt, LLC, for $235,104.00 to apply the HA5 product. On July 16,
2024, the City Council accepted the completed project for a final contract
amount of $216,517.00, a contract underrun of $18,587.00. Other project
expenses of $94.00.
Funding Breakdown
CIP Fund: $1,200,000.00
Other Fund: $728,121.00
Roger Stevens, Public Works Director
Accepted by the Sales Tax Oversight Committee
t� 22nd day of Septem der, 2025.
Stevens, City Clerk