HomeMy WebLinkAbout2026.03.23_Project Completion Report_Firestation 1 and 2 RenovationsPROJECT COMPLETION REPORT
PROJECT: Fire Station # 1 and Fire Station # 2 Renovations
DATE PROJECT WAS INITIATED: September 5, 2023
DATE PROJECT WAS COMPLETED: July 31, 2025
STAFF COMMENTS:
On August 16, 2022, the City Council approved an agreement with K+D Architects of
Owasso, Oklahoma. City Council awarded bids for both stations and approved an
agreement with Limestone Construction Inc., of Owasso, Oklahoma, for construction
management at risk services on September 5, 2023.
Fire Station #2 renovation work began on September 25, 2023, and was reopened on
March 6, 2024. The total expenses for Station # 2 were $2,709,974.00, of which $569,367.00
was expended from the CIP Fund.
Renovation work on Fire Station # I began on March 11, 2024, and was reopened on
September 9, 2024. The total expenses for Station # 1 were $2,131,278, of which
$460,178.00 was expended from the CIP Fund.
Following punch list inspections and completion, the City Council authorized final
payment to the construction contractor on November 28, 2024. Additional expenditures
for furniture, fixtures, and equipment are complete, and all expected invoices have
been paid.
Total project costs from the CIP Fund = $1,029,545.00
Additional funding was used to complete this project:
Half Penny (Fire) Fund
Ambulance Capital Fund
Ambulance Service Fund
Emergency Preparedness Budget
Accepted by the Sales Tax Oversight Committee
this 23rd day of March, 2026.
M.