HomeMy WebLinkAbout1998.06.16_OPWA AgendaPUBLIC NOTICE OF THE MEETING OF THE
OWASSO PUBLIC WORKS AUTHORITY
TYPE OF MEETING: Regular
DATE: June 16, 1998
TIME: 7:00 p.m.
PLACE: Council Chambers, Owasso Community Center
Notice and Agenda filed in the office of the City Clerk and posted on the City Hall bulletin
board at 4:00 p.m. on Friday, June 12, 1998.
Marcia Boutwell, Authority Secretary
AGENDA
1. Call to Order
2. Flag Salute
3. Roll Call
4. Consideration and Appropriate Action Relating to a Request for Approval of the Consent
Agenda. All matters listed under "Consent" are considered by the Trustees to be routine
and will be enacted by one motion. Any Trustee may, however, remove an item from
consent by request. A motion to adopt the Consent Agenda is non - debatable.
A. Approval of the Minutes of June 2, 1998 Regular Meeting.
Attachment #4 -A
B. Approval of Claims.
Attachment #4 -B
Owasso Public Works Authority '
June 16, 1998
Page 2 '
5. Consideration and Appropriate Action Relating to the Award of a Contract for the '
Construction of the Elm Creek Interceptor Sewer.
Mr Lutz
Attachment #5
The staff has completed the bidding process, reviewed the bids received, and will
recommend the award of a contract to HMG Inc, Kansas City, KS in the amount of '
$1,496,469.20, contingent upon receipt of funding for the project; and further recommends
that staff be authorized to develop documents and conduct negotiations for a low interest
bank loan and a revenue anticipation note. '
6. Consideration and Appropriate Action Relating to Change Order #3, a Change Order to a
Contract Between the Owasso Public Works Authority and Walters Morgan Construction
Co for the Construction of Improvements to the Wastewater Treatment Facility.
Mr Carr
Attachment #6
The staff will recommend Authority approval of Change Order #3 containing changes to the
contract as outlined in a letter dated June 9, 1998 and an acceptance letter dated June 10,
1998.
7. Consideration and Appropriate Action Relating to a Supplemental Appropriation to the
Refuse Collection Department of the OPWA Fund.
Ms Bishop
Mr Carr
Mr Ray
The staff will recommend a supplemental appropriation in the amount of $25,000 to offset
unanticipated equipment repairs and polycart purchases.
Owasso Public Works Authority
June 16, 1998
Page 3
8. Report from OPWA Manager
9. Report from OPWA Attorney
10. New Business
11. Adjournment
OWASSO PUBLIC WORKS AUTHORITY
MINUTES OF REGULAR MEETING
Tuesday, June 2, 1998
The Owasso Public Works Authority met in regular session on Tuesday, June 2, 1998 in the
Council Chambers at the Owasso Community Center per the Notice of Public Meeting and
Agenda posted on the City Hall bulletin board at 4:00 p.m. on Friday, May 29, 1998.
ITEM 1: CALL TO ORDER
Chairman Bode called the meeting to order at 7:20 p.m.
ITEM 2: FLAG SALUTE
The flag salute was given during the City Council meeting preceding this meeting.
ITEM 3: ROLL CALL
PRESENT
Denise Bode, Chair
Mark Wilken, Vice Chair
Mary Lou Barnhouse Trustee
Melinda Voss, Trustee
ABSENT
Tracy Standridge, Trustee
STAFF
Rodney J Ray, City Manager
Ronald D Cates, Authority Attorney
Marcia Boutwell, Authority Secretary
ITEM 4: CONSIDERATION AND APPROPRIATE ACTION RELATING TO A
REQUEST FOR APPROVAL OF THE CONSENT AGENDA.
A. Approval of the Minutes of May 19, 1998 Regular Meeting and May 26,
1998 Special Meeting.
B. Approval of Claims
C. Action Relating to the Extension of a Contract for Commercial Refuse
Service.
Mr Wilken moved, seconded by Ms Voss, to approve the consent agenda. The consent agenda
included minutes of the May 19, 1998 regular meeting and May 26, 1998 special meeting, by
reference made a part hereto. Item B on the consent agenda included the following claims:
(1) OPWA Fund $34,001.94; (2) OPWA Capital Improvement Fund $50,106.35; (3) OPWA
Sales Tax Fund $85,595.42; (4) Interfund Transfers $37,447.83; (5) Payroll $26,117.87.
Item C was a request to extend a contract with Waste Management for commercial refuse
collection for one year, with a 3.3 % increase in rates for the time period July 1, 1998 through
June 30, 1999.
Owasso Public Works Authority
AYE: Wilken, Voss, Barnhouse, Bode
NAY: None
Motion carried 4 -0.
ITEM 5: REPORT FROM OPWA MANAGER
No report.
ITEM 6: REPORT FROM OPWA ATTORNEY
No report.
ITEM 7: NEW BUSINESS
None.
ITEM 8: ADJOURNMENT
Mr Wilken moved, seconded by Ms Barnhouse, to adjourn.
AYE: Wilken, Barnhouse, Voss, Bode
NAY: None
Motion carried 4 -0, and the meeting was adjourned at 7:21 p.m.
Marcia Boutwell, Authority Secretary
2
Denise Bode, Chairperson
June 2, 1998
CITY OF OWASSO
OWASSO PUBLIC WORKS AUTHORITY
A/P CLAIMS REPORT
APAPVR PAGE:
PO # VENDOR DESCRIPTION AMOUNT
OPWA ADMINISTRATION
980036
980036
RONALD D CATES
LEGAL SERVICES
545.00
98O221
AT&T WIRELESS SERVICES
PHONE USE-CARR
35.01
980221
AT&T WIRELESS SERVICES
PHONE USE-ROBERTS
1O.65
982689
ENGINEERING NEWS RECORD
ANNUAL SUBSCRIPTION
74.00
982762
OFFICE DEPOT CARD PLAN
OFFICE SUPPLIES
26.94
98280 7
WAL-MART
OFFICE SUPPLIES
2O.84
982812
MAXIMUM CONTROL, INC.
SVS AIR CONDITIONER
40 00
982828
TREASURER PETTY CASH
REIMB PETTY CASH
20 .00
982828
TREASURER PETTY CASH
REIMB PETTY CASH
2.00
982828
TREASURER PETTY CASH
REIMB PETTY CASH
12.69
982859
PSO
5/98 USE
102.99
98286O
SOUTHWESTERN BELL TELE
5/98 PLEXAR
94.6O
--------------
DEPARTMENT TOTAL
1 684 72
UTILITY BILLING
------------------------------
982628
MARK MEYER
METER READER
276.75
982729
TYRONE DINKINS
METER READER
READER
354.90
153.90
98273O
BRAD SPARKMAN
METER
—
982731
RANDY ALEXANDER
METER READER
.
169 O5
—
982732
BRANDON HAMILTON
METER READER
77.85
982733
OSCAR MCLAURIN
METER READER
183.6O
DEPARTMENT TOTAL ====>
1 216 .. O5
WATER
______________________________
980221
AT&T WIRELESS SERVICES
PHONE USE-ALL
10.65
980423
WATER PRODUCTS INC
YALE UNIFORM RENTAL
WATER METERS 3/18/97
UNIFORM CLEAN/RENT
3,173.20
94.00
980656
982622
CITY OF TULSA
04/98 WATER PURCHASE
89,222.08
982652
GO SYSTEMS
FUEL O5/98
167.31
982653
CITY GARAGE
REPAIRS 05/98
SUPPLIES
163.71
86.79
982687
KIMBALL ACE HARDWARE
MAINT/REPAIR
982690
AMERICAN WATER WORKS
MEMBERSHIP RENEWAL
9O.0O
982693
GEORGE & GEORGE SAFETY
SAFETY EQUIPMENT
TUITION REIMBURSEMENT
79.45
180.00
982719
---
ERIC AYRES
—
982797
COOPER WHOLESALE
HYDRANT EXT KIT
3O7 90
982828
TREASURER PETTY CASH
MEETING EXPENSE
5/98 USE
28.97
204.48
982859
PSO
CITY OF OWASSO
OWASSO PUBLIC WORKS AUTHORITY
6/12/98 9:O3:O3 A/P CLAIMS REPORT APAPVR PAGE:
PO # VENDOR DESCRIPTION AMOUNT
---------- ------------------------- ------------------------- -------------
982860
SOUTHWESTERN BELL TELE
5/98 PLEXAR
10.65
51.30
982861
SOUTHWESTERN BELL TELE
5/98 NON-PLEXAR
982530
63.95
SAFETY LIGHTS
409.95
982652
GO SYSTEMS
FUEL 05/98
222.24
DEPARTMENT TOTAL ====>
CITY GARAGE
_____________
93,923.79
122.50
982684
WOODS PORTABLE WELDING
MOUNTING BRACKETS
45.00
982687
WASTEWATER
______________________________
TREATMENT PLANT
375.58
982693
GEORGE & GEORGE SAFETY
980656
YALE UNIFORM RENTAL
UNIFORM CLEAN/RENT
AMERICAN HOSE & SUPPLY
93.60
981574
FHC INC
WW MASTER PLAN 12/5/95
3,000.0O
130.00
982051
ADVANCED CHEMICAL
CHLORINE
540.34
405.00
982652
GO SYSTEMS
FUEL 05/98
31.21
982653
CITY GARAGE
REPAIRS 05/98
4.64
982691
ZEE MEDICAL SERVICE
FIRST AID SUPPLIES
25.60
982693
GEORGE & GEORGE SAFETY
SAFETY EQUIPMENT
29.65
982742
ROSE STATE COLLEGE
TUITION-SIMMS
100.00
982859
PSO
5/98 USE
6,103.49
982860
SOUTHWESTERN BELL TELE
5/98 PLEXAR
47.30
-------------
WASTEWATER COLLECTION
------------------------------
980221
AT&T WIRELESS SERVICES
PHONE USE-ALL
10.65
980656
YALE UNIFORM RENTAL
UNIFORM CLEAN/RENT
78.00
982530
AW DIRECT
SAFETY LIGHTS
409.95
982652
GO SYSTEMS
FUEL 05/98
222.24
982653
CITY GARAGE
REPAIRS 05/98
122.50
982684
WOODS PORTABLE WELDING
MOUNTING BRACKETS
45.00
982687
KIMBALL ACE HARDWARE
MAINT/REPAIR SUPPLIES
375.58
982693
GEORGE & GEORGE SAFETY
SAFETY EQUIPMENT
79.45
982753
AMERICAN HOSE & SUPPLY
JETTER RODDER HOSE
25.00
982800
JONNY ON THE SPOT
RENTALS-TOILET
130.00
982859
PSO
5/98 USE
540.34
982861
SOUTHWESTERN BELL TELE
5/98 NON-PLEXAR
324.59
DEPARTMENT TOTAL =:> 2,363.30
REFUSE COLLECTIONS
------------------------------
980656
YALE UNIFORM RENTAL
UNIFORM CLEAN/RENT
93.20
982476
WILLIAMS REFUSE EQUIPMENT
GREEN POLYCARTS 7/15/97
5,700.00
982530
AW DIRECT
SAFETY LIGHTS
409.95
982561
WILLIAMS REFUSE EQUIPMENT
RED POLYCARTS 3/18/97
2,950.00
CITY OF
OWASSO
OWASSO PUBLIC
WORKS AUTHORITY
PAGE:
6/12/98
p:O3:03 A/P CLAIMS REPORT
APAPVR
PO #
VENDOR
DESCRIPTION
AMOUNT
982561
WILLIAMS REFUSE EQUIPMENT
HALF-HINGES FOR LIDS
COMMERCIAL REFUSE 5/98
18O.00
14,O43.81
982644
WASTE MANAGEMENT OF OKLA
982652
GO SYSTEMS
FUEL O5/98
459.81
982652
GO SYSTEMS
FUEL 05/98
185.33
982653
CITY GARAGE
REPAIRS 05/98
75O.92
35O.81
982653
CITY GARAGE
REPAIRS O5/98
982687
KIMBALL ACE HARDWARE
MAINT/REPAIR SUPPLIES
26.O4
982692
DOZIER PRINTING
ROUTE CHANGE NOTICES
39.65
38.97
982693
GEORGE & GEORGE SAFETY
SAFETY EQUIPMENT
982727
ALSUMA TRUCK REPAIR INC
REPAIR 2 TRUCKS
871.O5
TMENT TOTAL ====>
DEPARTMENT
6 , 099 . 54
RECYCLE CENTER
-----------------_------------
98O65 6
YAE UNIFORM RENTAL
UNIFORM CLEAN/RENT
SUPPLIES
18.4O
.99
982687
KIMBALL ACE HARDWARE
MAINT/REPAIR
9828O1
RAINBOW CONCRETE CO
CONCRETE
61.5O
982859
98286O
PSO
SOUTHWESTERN BELL TELE
5/98 USE
5/98 PLEXAR
1O6.57
23.65
....................................................
DEPARTMENT TOTAL ====>
11 11
2 .
-------------
FUND TOTAL ====>
13 5 339 0O
CITY OF
OWASSO
OPWA
CAPITAL
IMPROVEMENT
FUND
6/12/98 9:O3:0 3
A/P
CLAIMS
REPORT
APAPVR
PO # VENDOR
AMOUNT
DEBT SERVICE
982778 BANK ONE
ADMINISTRATION
FEE
1,50 O.O0
DEPARTMENT TOTAL
====>
1,5OO.00
WASTEWATER
980309 HUB + GARVER
WWTP
CONST 9103196
6,24O.00
DEPARTMENT TOTAL
====>
6,24O.00
WWTP IMPROVEMENTS
980023 WALTERS MORGAN C0�STRUCTI
WWTP
IMP 111/05/96
10 0 ,278.39
DEPARTMENT TOTAL
====>
100, 27f
FUND TOTAL ====>
-------------
108,018.39
CITY OF OWASSO
OPWA SALES TAX FUND
6/12/98 9:O3:03
A/F CLAIMS REPORT
DESCRIPTION
REVENUE BONDS AMOUNT
980002 BANK ONE TRUST CO, NA
DEPARTMENT TOTAL
FUND TOTAL ====>
GRAND TOTAL ====>
97 REVENUE BONDS
89,550.00
-------------
89,550.O0
-------------
89,55O.00
-------------
399,993.49
OWASSO PUBLIC WORKS AUTHORITY
PAYROLL PAYMENT REPORT
PAY PERIOD ENDING DATE 06/06/98
OVERTIME TOTAL
DEPARTMENT EXPENSES EXPENSES
OPWA Ad
nunstrat
0.00' $5,006 67
Utility Billing 0.00 3.704.85
Wastewater 421.26 6,037.17
Wastewater Collection : ;::393 81
5,638 97
Refuse 135.71 3.985.52
FUND'rQfiAL $3p06 43 $32,459 91
APPROVED: 06/16/98
Chairman
Trustee
Trustee
MEMORANDUM
TO: HONORABLE CHAIR AND TRUSTEES
OWASSO PUBLIC WORKS AUTHORITY
FROM: F. ROBERT CARR, JR., P.E.
PUBLIC WORKS DIRECTOR
SUBJECT: ELM CREEK INTERCEPTOR SEWER
CONTRACT AWARD
DATE: June 10, 1998
BACKGROUND:
The impact of growth places demands on the infrastructure of the city, specifically on the
wastewater collection and treatment system. It is the policy of the Owasso Public Works
Authority to be proactive, rather than reactive in matters of growth and development. On
January 6, 1998, Owasso Public Works Authority Resolution No. 98 -01 adopted the 1997
Wastewater Master Plan as a policy statement for the extension, expansion and development of
privately - financed and publicly - financed improvements of the City of Owasso municipal
wastewater collection and treatment system. System needs are detailed in the Master Plan based
on the present, 5 -, 10- and 20 -year growth projections.
Proposed development in the Elm Creek drainage area has been occurring as described in the
Master Plan. Development plans have been submitted that will require wastewater collection
for essentially the entire undeveloped area south of 86th Street North between North 129th E.
Avenue and North 145 E. Avenue (Albertson's and Owasso Golf and Athletic Club). Other
development is likely to occur north and east of 86th Street North and North 145th E. Avenue,
as well as with continued development north of 86th Street North west of North 145th E.
Avenue (Silvercreek Addition).
Recent activity involving the undeveloped area south of 86th Street North between North 129th
E. Avenue and North 145 E. Avenue (Albertson's and Owasso Golf and Athletic Club) has
resulted in a long -term method to provide wastewater collection. Consulting engineers (Grafton,
Tull & Associates, Inc.) for Lindsey Properties (Owasso Golf and Athletic Club) have
determined that constructing the interceptor would eliminate costs of constructing interim lift
stations presented in the Master Plan that are intended to be rather short - lived. The majority
of expense of lift station and force main construction would be lost once the interceptor is
ultimately constructed. Crafton, Tull has proposed that Lindsey construct the portion of the
interceptor from 76th Street North to a point on the south side of the Owasso Golf and Athletic
Club property. The portion of the interceptor from the 117th E. Avenue lift station to 76th
Street North would be constructed by the City of Owasso. Construction of the interceptor in this
ELM CREEK INTERCEPTOR AWARD
JUNE 10, 1998
PAGE 2
manner (i.e., from south to north) will enable wastewater collection to be accomplished without
the need for interim facilities and enable the system easily to be extended north. Costs of
construction will be allocated to appropriate undeveloped property in the basin in order to
proportionately distribute engineering, easement acquisition and construction expenses to present
and future users of the interceptor.
ELM CREEK INTERCEPTOR PROJECT DESCRIPTION:
The interceptor is sized and designed to carry additional flows for the total area to be served
ultimately. The interceptor has been designed as 21 -inch diameter and essentially is to be built
adjacent to Elm Creek in the flood plain. The concept for construction is shown on the attached
Location Map.
BID ANALYSIS:
Crafton, Tull & Associates have developed design documents and specifications for the
interceptor. Public Works Department Engineering Division staff have reviewed the documents.
The final plans were approved by Engineering and an advertisement was published on May 7,
1998. A Pre -bid Conference was conducted on May 27, 1998. Bids were opened on June 9,
1998. Five (5) bids were received and summarized as follows:
Bidder
Base Bid
Deductive Alternate
F Total Bid
HMG, Inc. (Kansas City, KS)
$1,551,469.20
$55,000.00
$1,496,469.20
McGuire Brothers (Tulsa, OK)
1, 816, 049.00
15, 000.00
1, 801, 049.00
Ram Engineering and Construction (Tulsa,
OK)
1,684,170.90
10, 000.00
1,674,170.90
T -G Excavating (Catoosa, OK)
2, 073, 039.00
40, 000.00
2, 033, 039.00
Tam Har, Inc. (Sapulpa, OK)
Not submitted
35,000.00
1,612,580.00
7
0I
The solicitation required submittal of a base bid (for construction of cast -in -place concrete '
manholes) and a deductive alternate bid (for construction of pre -cast concrete manholes). The
apparent low bid was received from HMG, Inc., Kansas City, Kansas for both the base and
deductive alternate bids. Staff will recommend that the award be made based on the deductive '
alternate bid. The Engineer's estimate is $1,587,382.00.
I I
ELM CREEK INTERCEPTOR AWARD
JUNE 10, 1998
PAGE 3
PROJECT SCHEDULE:
The proposed schedule for the project is as follows:
Notice to Proceed June 24
Construction Complete November 21 (150 calendar days)
The developer desires to have the first phase of apartments completed around October 1st. As
a result, means to expedite construction will be evaluated.
PROJECT FUNDING:
The City has historically required those infrastructure improvements necessary to the
development of property to be funded by the developer. The only exception to that policy was
the construction of the "Ranch Creek" interceptor (built in the early eighties and located on the
western border of the city). In that case, the City paid for the improvements using the proceeds
of a bond.
In this case, the staff has recommended, and the Trustees have reviewed a plan that will provide
the initial capital cost through the public sector, with an eventual recouping of those funds
through an assessment to each piece of property located in the line's service area. The concept
is to require each tract of land to pay its share of the cost of the project when the property is
developed and "tie in" to the system is requested. This concept allows the City to avoid
temporary facilities and lift stations in favor of a permanent solution.
The staff has researched the options available and will recommend that the project be funded
through the combined use of a low- interest private sector loan and "revenue anticipation note"
issued by the OPWA to the City of Owasso (essentially a self - funded loan from the City's
various fund reserves). Under this concept, approximately one million dollars would be
borrowed from a local bank at a low- interest rate (loans to the OPWA are tax exempt for the
bank) and the remainder of the funds (approximately $700,000) supplied by the City through an
"investment" on an OPWA revenue anticipation note. Both loans would be retired from
revenues generated by the "payback" requirement. It should be noted that the staff projects an
estimated $185,000 will not be repaid because there is some land in that area that may never
develop.
The staff has requested quotes from all three local banks on a low interest loan and is in the
process of reviewing those quotes. The staff has also met with the City's financial advisor
(Keith McDonald) and bond counsel (Alan Brooks) to enlist their assistance in ensuring such a
loan will not have an adverse impact on our already issued debt. Both have advised that the
proposed concept is valid and can work as long as the bank loan does not exceed 1.5 million
dollars and the successful bank recognizes the loan cannot be secured by a "first" lien.
ELM CREEK INTERCEPTOR AWARD ,
JUNE 10, 1998
PAGE 4 ,
The City Council discussed this concept in a work session in May, and the staff is in the initial
stages of drafting the necessary documents (Mr Brooks has volunteered to complete the draft). '
The staff (Ms Bishop & Mr Ray) is also in the first stages of negotiating the interest rate for the
low interest loan component of the package.
The recommendation (below) requests authorization for the staff to finalize this funding concept ;
by completing loan negotiations and developing the documents for the revenue anticipation note.
It should be noted that finalizing the financing package is critical because state law will not allow '
final award of the contract until funds are appropriated.
RECOMIVIENDATION:
The staff recommends that the Trustees award a contract for the construction of the Elm Creek
Interceptor to HMG, Inc., Kansas City, KS in the amount of $1,496,469.20, contingent upon
receipt of funding for the project, and further authorize the staff to develop documents and
conduct negotiations for a low interest bank loan and a revenue anticipation note, provided
however, such financing be presented to the Trustees for final approval prior to execution.
ATTACHMENTS:
1. Location Map
2. Bid Tabulation
MEMORANDUM
TO:
FROM:
SUBJECT:
HONORABLE CHAIR AND TRUSTEES
OWASSO PUBLIC WORKS AUTHORITY
F. ROBERT CARR, JR., P.E.
PUBLIC WORKS DIRECTOR
CHANGE ORDER NUMBER 3 -
WASTEWATER TREATMENT PLANT CONSTRUCTION
DATE: June 11, 1998
BACKGROUND:
A contract for the construction of the Wastewater Treatment Plant improvements Phase I was
awarded to Walters - Morgan Construction, Inc., Manhattan, KS on November 5, 1996 in the amount
of $1,923,900. While performing excavation work near the location of the clarifiers, Walters- Morgan
encountered rock that the contractor believes was unforeseen and warranted additional payment and
time extension.
As a result of this condition, a meeting was held on November 3, 1997 that included representatives
of Walters - Morgan, Larry Lipe (Walters -Morgan attorney), Ron Cates (City Attorney), Bruce Bellen
(HUB +Garver Project Manager for construction engineering services to the OPWA) and Robert
Carr. Subsequent correspondence and telephone conversations have been held concerning the issue
and the opinion of HUB +Garver is that the contractor is entitled to additional compensation and/or
time, but determination of reasonable amounts of each was questioned. Additional cost of
approximately $63,000 and 31 additional calendar days was proposed by the contractor.
Following review of their claim by HUB +Garver, correspondence to Walters- Morgan dated March
19, 1998 proposed payment in the amount of $17,500 and an additional fourteen (14) working days
for the project. On May 11, 1998, the attorney (Larry Lipe) for Walters -Morgan responded with a
potential resolution listing eighteen (18) items for consideration (see attachment). A summary of the
items and cost breakdown for each item was evaluated by HUB +Garver in a letter dated May 27,
1998 (see attachment).
Page 2
Change Order No. 3
Wastewater Treatment Plant Construction
CHANGE ORDER NO.3 PROVISIONS
Following review of the items by city staff Mr. Cates submitted another proposal dated June 9, 1998
with the following items:
-Project would have a substantial completion date of June 23, 1998 with final punch list on
or before June 23, 1998
• Final completion date shall be August 7, 1998
• Contractor will:
- complete final punch list on or before August 7, 1998
- withdraw the "rock claim" against the city
- install one (1) additional 12 foot fence gate
- adjust effluent manhole at the oxidation ditch
- leave in -place "as -is" the 96 -inch steel culvert creek crossing
- 2500 sq. yards of sod and three (3) acres of seeding
- asphalt paving to control structure
- provide drainage on west side of access road
- install base course rock in lieu of treated subgrade for asphalt paving
- complete remaining work included in the original contract
• City will:
- not assess liquidated damages against the Contractor unless the substantial or final
completion dates are not met
- not assess any engineering or inspection costs against the Contractor
- release contract retainage in full no later than thirty (30) days after final completion
Taking into consideration the above items, the Authority will pay an additional sum of $46,890.00.
Walters- Morgan has agreed to these items (see letter dated June 10, 1998).
The resultant final construction amount will be $1,953,375.86. The total represents $29,475.86
above the original contract amount.
FUNDING SOURCE:
The Oklahoma Water Resources Board project budget is approved in the amount of $2,900,035.70.
Within the budget is $110,412.67 for contingencies. All costs associated with the Change Order
above the original approved contract amount can be paid from contingencies.
Page 3
Change Order No. 3
Wastewater Treatment Plant Construction
RECOMMENDATION:
Staff recommends the Trustees approval of changes to the contract for the Wastewater Treatment
Plant Phase I Improvements with Walters -Morgan Construction Co. for purposes of implementation
of the settlement as outlined in the June 9, 1998 letter by Ronald D. Cates and as accepted by
correspondence by Conner & Winters dated June 10, 1998 and authorization of the Chair to execute
a Change Order reflecting these items and any other documentation relating thereto.
ATTACHMENTS:
1. Conner & Winters letter dated June 10, 1998 accepting changes
2. Ronald D. Cates letter dated June 9, 1998 with counter proposal
3. HUB +Garver letter dated May 27, 1998 evaluating proposal
4. Conner & Winters letter dated May 11, 1998 with proposal
5. Ronald D. Cates letter dated March 19, 1998 with proposal for $17,500 and 14 working
days
6. OWRB project budget
CHTES- LUNDERWOOD
TC'LS.x
V00 FIRST PLACE MwE3
I' EAST FIFTH STREET
TLL: A. QK 41,23.4344
1913) 556 -5 711
F,-LX (915158E 8991
OKLATTOMA cm'
ONE LEADERSRIP SQUARZ
1 NORTH ROBINSON, SIATE 1700
OLLAROMA CITY, OK %3193.7101
I4Q'1 dl'- ^11
PAY (1751
9185829166
CONNER &- WINTERS
P . O
PF :OFESS10a:�L COPPr�R;'lOn
NORTHWEST .%RKANSAS
LAWYERS
S1TTe :oi0
1S0 iYEST CENTER S'rR,�HT
3704 FIRST FLACE TOWER
FAYETTEVILLS,AR7
1500 582511
15 EAST FIFTH STREET
F -AX (501) 5? ? -la2p
TULSA. QUAHO'MA 74109 -4344
WASWING O N, O.C.
SUITE 06
W9 iTEF'S ZiR F.C'T �� 11AFR
1 101 S iN ENTEENT14 STREET, N . W
(Q 18) SW8512
WASHINUTON, 0 C. z1NI3h -47r<
F, %N (9 1$) 599 -9 164
(:G:1 78)47; 1
FATS f "lVa' 153 -!7:G
WRITEk'S E -MAIL .ADDRESS
111pe "&C W14 W.C6R1
June 10, 1998
VIA )FACSIMILE & MAIL
Ronald D. Cates, Esq.
525 East Main Street, Suite 680
Tulsa, OK 74103 -4507
Re: Owasso WWTP Phase I Imnrove.rnen
Dear Ron:
Walters - Morgan Construction, Tnc. accepts the offer as set forth in your letter of June 9,1998.
Please advise me when the settlement has been approved. Walters- Morgan is going forward with
the items 1 -17 in anticipation of the approval by the appropriate city authority.
Sincerely,
CONNER & WINTERS
Larry B. Lipe
a
L
N
L.BL:md '
cc: John Walters (via facsimile)
P: (6 -10 -98 ).wpd
RONALD D. CATES
Attorney at Law
Suite 630, PurkCentre
52S South Main
Tulsa, Oklahoma 74103
tune 9, 1998
FAX 918-582-0166
VIAFACSiM1LE
Larry B. Lipe, Esquire
Conner & W utters
3700 First Place Tower
15 East 5th Street
Tulsa, Oklahoma 74113 -4344
In Re- Owasso Waste Water Treatment Plant, Phase I Improvements
Dear Larry:
I am corresponding for purposes of confirmation of my conversation with your off
regarding the above referenced matter. I have met with the City Manager, Public Works Director
and the Consulting Engineer regarding the settlement of the remaining project issues. As a result
of such meeting I have been authorized, subject to approval of the Owasso Public Works
Authority, to make the following settlement offer. The Owasso Public 'Works authority would
agree to the following items as outlined in your letter ofMaY 1 I. 1998, to wit.
The parties would agree that the project would have a Substantial Completion Date of
iune 23, 1998, and the City shall prepare a Final punchi.st of items on or before June 23,
1998,
2 The Final Completion Date shall be August 7, 1998 which will include completion of all
Punchlist items by that daze,
3 The City will not incorporate those item negotiated directly with third party vendors into
the Punchlist, Substantial Completion Date, or the Final Completion Date;
4 The Contractor will complete the Final Punchlist on or before August 7, 1998,
4. The Contractor will be granted force majeure time extensions as appropriate for impacted
Punchlist items and rev. lining contract work, 6 The Contractor will withdraw their "Rock Ciai:- ,:7ainst the City,
7 The Contractor will install one (1) additional i L fence gate,
S. The Contractor will adjust the effluent manhole at the Oxidation Ditch V -0"a-;
CITY OF OWASSO
9. The Contractor will leave in place "As Is" the 96" steel culvert creek czossrng,
Ip. The Contractor veil! uzstall 2500 syds of bermuda sod and tlu-ce (3) acres ofbermuda
seeding,
I I The Contractor will install asphalt paving for vehicle access to the Control Structure;
P.03
12. The Contractor will install additional asphalt paving, regrading, drainage pipe, and soil
erosion protection required to provide proper drainage on the west side of the access
road,
13. The Contractor will install base course rock in lieu of lime treated subgrade far asphalt
paving;
14. The Contractor will complete the remaining work included in the original contract except
as modified above,
15. The City will not assess Liquidated Damages against the Contractor unless the Substantial
or Final Completion Dates are not met,
16. The City will not assess any En&eering or Inspection costs against the Contractor,
17, The City will release Contract Retainage in full no later than thirty (30) days after Final
Completion.
The Authority, taking into consideration the above set forth items, will pay unto Walters Morgan
Construction, Inc. an additional sum of S46, 890.04. Such payment would result in the actual
final contract price being Si, 953, 375. 86. This amount is determined in the following mariner, to
wit
Amount owed including Change Order No. I
and Work Directives 5 through 10
Balance of Allowance
Proposed Change Order No. 2
Total Final Construction Amount
$1,906,485.86
$17,414. 1
$29.475.86
$1, 953, 375, 86
CITY OF OWASSO
P. 04
Due to the Authority meetijl$ schedule it is imperative that I receive verbal or written notice of
your client's acceptance or rejection of this final offer by June 11, 1998 Thanking you in
advance for your attention hereto, I remain.
cc. Jeff Hancock
cc. F. Robert Carr, P.E.
CC. Rodney Ray
cc. Jay Updike, P E.
Sin y,
Ran Cates
Authority Attorney
T=A,
]700 F =T ?Lk CE TOW —r
IS EAST FIF AS7REPT
TULS& OA 74103 -4344
i,ol8) ssr., -3:31
• FA:<f91 n)SgG -1{CKZ
0kI AU0x,\ Crry
Q-a8 LF iDEMkU SQUAB e
231 Nt7ATM RO8XA0N; gjgM 1700
OKLAHOMA CITY• OK'4102.7301
(405) 272• Ph
FAX (4W) .3Z -1647
CATES- ='UNDERWOOD 9185820166
ci
CONNER & WINTERS
A PROFF$5IOVAL CORPOR ATtu.v
LA«l•ERS
1%(Ll FIRST PLAcr: Tower. '
15 EAST Ftf7'1-t STRFEA
+aZA, OKLAHOMA 74103.431.1
_ ++I
WRITIM'S UMECT NLNMCR
(918)580-5512
FAX (9 t8) j99.9S >e
t4'xr; EiVS t- :1,41L itL�LRP$S
Iliptvsk wl;tw'.�ritll
I
l
May 11, 1998
VIA F CS1�11IiE
Ronald D. Cates, Esq.
525.East Main Street, Suite 680
Tulsa; 0K 74103 -4507
Re- 01vasso V W'!'P Phase I 1 - rovements
Dear Ron,
P, 02
P. 02
MO4THt \'CST AXtXA, SAL
St1i. E .Dr,
300 WF,ST CENTTR STRFJiY '
FAYET'I'YVILLB, AR'2701.6JA1
(561)582.5711
587.1425
WASHINGTQN.n.r.
S1.R7'S 605
1102 SL E3'lMENTH STO,2 -r, ti.`N.
WASY)NUTON,17.C. ,0036-1704
1=112) 787.5711
Im an effort to resolve any remaining disputes concerning this project and to avoid futLtxe
issuer, Falters Morgan Construction(, Inc. offers the follo,,ving proposal as a compromise and
comprehensive settlement proposal, Neither Walters Morgan noc the City would admit liability or
fault in connection with the project, but rather enter into this settlement to resolve all outstanding
disputes-,
2.
3.
4-
5.
.1
The parties would agree that the project would have a SuOstantial Complction Datc of June
23, 1998, and the City slta.11 prepare a Final Punchlist of >erns on or before June 23, 1998;
The Final Completion ]=late shall be August 7, 1998 wh>�ch will include completion of all
Punchlist items by that date;
The City will not incorporate those items negotiated direct Ily tivith third party vendors into the
Punchlist, Substantial Completion Date, or the Final C;oAipletion Date;
i
The Contractor will complete the Final Punchlist on or before ,august 7. 1998;
The Contractor will be granted farce ..=Jeure time exterlsions as appropriate for impacted
PlIncl list items and remaining contract wort:;
The Contractor will withdraw their "Rock Claim" agains I t the City;
7. The Contractor will install one (1 ) additional 12' fence gate;
I
S. The Contractor will adjust the effluent manhole at the 0 i.dation Ditch 1' -Q"
P
L
GATES= U N D E R P. 03
02 1604 �5k9�140, 7
Ronald D, Cates, Esq.
May 11, 1998
Page 2c
9. The Contractor will leave in place "As Is" the 96" steel culvert creek 0 ro ng;
10. The Contractor will install 2500 syds of bennuda sod and tree (3 )) acres of bermuda seeding;
1-1 The Contractor will install asphalt paving for vehicle acc to the Control Structure:
12. The Contractor will install additional asphalt paving, regrading, drainage pipe, and soil
erosion protection required: to provide proper drainage on the west side of the access road;
13. The Contractor will install base course rock in lieu of Mime treated subgradc for asphalt
paving,,
14. The Contractor will complete the remaining work included in the original contract except as
modified above;
15, The City will not assess Liquidated Damages against the Contractor unless the Substantial
or Final Completion Dates are not met;
1.6. The City will not assess any Engineering or Inspection costs aggainst the Contractor;
17, The City AAH release Contract Retairiage- in full no latet than thirty (30) days, after Final
Completion; and
19. In consideration of the above items, the City will pay the. Contractor an additional $66,000
over the Contract price.
We will be happy to sit dozen with. you and discuss any of these iterns. If there are any
questions about any of the technical issues involved in this settlement, representatives of the City
or its engineering f=m should feel free to contact Walters Moran directly. I hope that this will
allow a complete resolution and settlement of all outstanding issues between the City a:ad Walters
Morgan. I look forward to hearing from you.
Sincerely,
CONNER & WIN I EK5
L&rry B. Lipe
LBL -md
PA3 719272-007%mlertcttes
5415 So, 125th East Avenue
Elude 29,
Tulsa, Oklahoma 70-1 A$
918- 250-5922
FAX 918.250-e5P9
HUB +Gamer
A G*rverPluaCompany
May 27, 1998
To: F. Robert Carr
From: Jay Updike
Re: Owasso Wastewater Treatment Plant Expamian - Phase 1 UPI 'jMMM
We have reviewed the attached letter of May 11, 1998 to Mr. Ronald Cates conceraing a final
settlement of work on the above rdmatced project.
Sit to the receipt of this letter and with the permission of Mr. Cates, offi',oe we rectived
the attached letter of May 26. 1998 providing a requested cost breakdown of several of the
items.
A sma ma:y of the items and the amounts requested by the contractor are as follows:
. h&M'&- SM= AMg=
(per letter of 5/11198)
7
Additional 12' Gate
8 Raise manhole at
Oxidation Ditch
9 96" Culvert
10 Sodding/,Seeding
11 Asphalt to control structure
12 Paving, grading and pipe
Along access road 842.00
GW,refl Carver L IM ROek ArOansas • Diva Garver. Jackson. Mm i"jpor. UxtM 1. MiSSi=PP
Ht,JB4G4tvot, 74dsat. LAe -G -er, LO,wSnik. kzfWcky. N,5rrAJb& -f, Lnd m - WTW,Garver, Pum'sw/k. Alabama. Bnantvrood, 7krhrd59Be • t-mM- yjGarver, Merko Cey
$968.00
238.00
10,924.00
(1,064.00)
849.00
Mr. F. Robert Carr
May 27, 1998
Mcmo - Page Two
13 Aggregate base in lieu of
line stabilizadmi
(2,443.00)
18 Rock excavation for clarifiers
55- 697.0(}
TOTAL ADDITIONAL AMOUNT REQUESTED
$66,011.00
A copy of a memo to your office providing a cunvnt project budget including all change orders
and work directives awproved to date is also attached As shown the current budget includes
$126,824.81 in project contingcacics.
Our recommendation con each of the items is as follows:
Recommended
Item No. S-cw—e
Amo= of Action
Add 12' Gate
$968.04
8 Raise manhole at
Oxidation Ditch
238.00
9 96" Culvert
0.00
10 Soddtng/Sredmg
11 Asphalt to omtrol structurc
12 Paving, grading and pipe
Along aoms road
13 Rock base in tiff of
time stabilisation
18 Rock Claim Offer
TOTAL RECOWAFFNDED OFFER
TOTAL AMOUNT REQUIRED ABOVE CONTRACT PRICE
cc_ Rodney Ray
CC*" Ron Cates
(Have oonCTvctOr rciftove)
(1,064.00)
849.00
842.00
(2,443.00)
4,
$41,890.00
$24,121.00
I
TOTPL P.0-)
RONALD D. CATES
Attorney at Law
Suite 680, ParkCentre
525 South Main
Tulsa, Oklahoma 74103
918 - 582 -7447
March 19, 1998
Mr. Larry B. Lipe, Esq.
Conner & Winters
3700 First Place Tower
15 East 5th Street
Tulsa, Oklahoma 74103 -4344
FP
f V11AR 2 3 5zg 93
---- ---- -- - - -- --/
FAX 918 -582 -0166
via facsimile - 918/599 -9404
original to follow in mail
In Re: Owasso Waste Water Treatment Plant Phase I Improvements - Walters
Morgan Construction, Inc.
Dear Mr. Lipe:
In accordance with our telephone conversation of the 18th day of March, 1998, I am
corresponding for purposes of confirmation of the matters discussed in such telephone
conversation. As I indicated, F. Robert Carr, Jr., P.E., the Director of Public Works, Jay Updike,
P.E. of HUB +Garver, Project Representative and I have now had an opportunity to review your
submission dated November 18, 1997, as well as supplementary documentation consisting of an
itemization of amount of additional compensation ciaimed as well as Walters Morgan
Construction, Inc., bid tabulation for this project.
For the sake of brevity I will outline the issues as I see them to exist. Such issues are as
follows, to -wit:
Whether Walters Morgan Construction, Inc., is entitled to additional compensation and /or
time under paragraph seventeen (17) of the General Conditions of the Contract for extra work it
performed due to encountering an unanticipated massive hard rock formation during excavation;
and, If Walters Morgan Construction_, Inc., is entitled to additional compensation and /or time,
how much compensation and /or additional time is reasonable.
As set forth in your memorandum of November 18, 1997, although Walters Morgan
Construction, Inc., acknowledges the disclaimer language set forth in the agreement, it
nevertheless relies upon paragraph seventeen (17) of the General Conditions set forth in the
Contract. In this respect, our investigation of this matter indicates that some unsuccessful bidders
did include within their bid amounts for rock blasting while on the other hand other bidders did
not include costs for rock blasting anticipating they could excavate the rock with an impactor.
Based on such research, it is clear that the bidders on the project made different assumptions from
the information provided to them by the Owasso Public Works Authority. Accordingly, the
clarity of the disclaimer utilized in the bid solicitation and its enforceability over the general
provisions of the contract set forth in paragraph seventeen (17) thereof remains an issue.
Mr. Larry B. Lipe
March 19, 1998
Page 2
In addition to the foregoing, assuming for the sake of argument that paragraph seventeen
(17) of the General Conditions would prevail, as you are aware, Walters Morgan Construction,
Inc., did not comply with the requirements set forth in 17.1 thereof regarding submission of
written notice of such subsurface conditions prior to performance of the additional work. As you
are aware, I am sure, the provisions of paragraph 17.'l of the General Conditions of the Contract
are placed in such contract for purposes of affording the public agency the opportunity to evaluate
whether or not there are latent physical conditions at the site differing materially from those
indicated in the contract documents as well as afford the public agency an opportunity to analyze
and ascertain any alternative design and /or construction to avoid the latent physical condition and
resultant additional work so that no equitable adjustment would need be made in the contract
documents relating to compensation and time. Accordingly, the failure on the part of Walters
Morgan Construction, Inc., to provide the contractually required written notice has effectively
precluded the Owasso Public Works Authority from exercising such contractual right and
opportunity to avoid the additional costs and time as set forth in Walters Morgan Construction,
Inc., claim.
Notwithstanding the foregoing, for the sake of settlement purposes only, my client has
analyzed the claim for additional costs associated with rock removal at the Owasso Waste Water
Treatment Plant from the standpoint of if in fact Walters Morgan Construction, Inc., is entitled to
additional compensation and /or time, then how much compensation and /or additional time is
reasonable. In that regard, Jay Updike, P.E., with Hub +Garver has reviewed the submission of
your client denoted Additional Costs Associated With Rock Removal At Owasso WWTP. In that
respect, it is Mr. Updike's position that an inordinate amount of time was expended by employees
of your client, after discovery of the subsurface condition. Specifically, based upon the
Inspector's reports, employees of Walters Morgan Construction, Inc., attempted to mechanically
excavate the rock for approximately three weeks before deciding to blast the rock. This
1 mechanical effort is included in your client's claim along with extended job site oversight for an
unsuccessful effort. Accordingly, it is our position that the Owasso Public Works Authority
should not be responsible for the failure to mechanically excavate the rock or the additional fob
site overhead associated with these efforts. Based upon such position, Mr. Updike has calculated
what we determine would be reasonable additional costs associated with rock removal at the
Owasso Waste Water Treatment Plant if the Owasso Public Works Authority has any liability
therefor. I have provided you a copy of such calculation with this correspondence.
Finally, as I indicated in our telephone conversation, an amicable and expeditious
resolution of this matter is affected by the amount of project funds remaining in light of
anticipated work change directives. I have been advised as recently as the 17th day of March,
1998, that as a result of conversations between the Owasso Public Works Authority's project
' representative and representatives of your client additional work charge directives will be
necessary.
Mr. Larry B. Lipe
March 19, 1998
Page 3
Based on the foregoing, for settlement purposes only, I am authorized to state that my
client is prepared to recommend to the City Council of the City of Owasso, Oklahoma, a
proposed settlement of the issues presented by the rock removal at the Owasso Waste Water
Treatment Plant by payment to your client of the sum of seventeen thousand five hundred dollars
($17,500.00) as well as providing an additional fourteen (14) working days on this project. As
we discussed, based upon conversations from employees of your ciient, although additional time
has not been specifically requested, it is anticipated such is needed and accordingly the additional
fourteen (14) days does not only have monetary value to your client but likewise increases project
representative costs to my client. Therefore, in the spirit of compromise, I would hope that your
client would look favorably upon this effort on the part of the Owasso Public Works Authority to
amicably and expeditiously resolve this matter and bring this project to completion without any
remaining contractual issues.
After you have had an opportunity to review this wit o r client, please advise.
Sirc r ,
Ronald D. Cates
Attorney for
the Owasso Public Works Authority
RDC /nhc
encl.
xc: F. Robert Carr, Jr., P.E.
Director of Public Works
Jay Updike, P.E.
HUB +Garver Project Representative
3709 - 017.111
PAGE 1
ADDITIONAL COSTS ASSOCIATED WITH ROCK REMOVAL AT OWASSO WWTP
-------------------------------
Labor
Mat
Equip
Sub.
Description
Quan
Cost
Cost
Cost
Cost
BLASTING
Dykon Subcontract
1 LS
$0.00
$0.00
$0.00
$7,150.00
750
BLASTING SUPPORT
5')
IAP
WMCI Raw Labor
1 LS
$1,960.50
$0.00
$0.00
$0.00
P,T, & 1
1 LS
$0.00
$694.02
$0.00
$0.00
6�4 w
Hyundai 290 Track Exc w/ bucket
27 HR
$0.00
$0.00
$2,565.00
$0.00
J5
Cat 950E Loader
24 HR
$0.00
$0.00
$1,560.00
$0.00
!r, W o7
Dump Trucks
6 HR
$0.00
$0.00
$180.00
$0.00
ADDITIONAL HOE -RAM WORK WITH
HYUNDAI 290 & RAM
WMCI Raw Labor
1 LS
$172it'
$0.00
$0.00
$0.00
P,T, & I
1 LS
$0.00
Sr455-77
$0.00
$0.00
Equipment Transportation
1088 MI
$0.00
$2;Qt2
$0.00
$0.00
e,
Hyundai 290 Track Exc w/ Ram
70 HR
$0.00
$0.00
$5,8D0'OQ
$0.00
d -
EXTENDED JOBSITE OVERHEAD
r %: u#DY
a 30A
-
$0.00
$0.00
$83696&
$'F8;`t94.92
$14.t05_. 0
Sr7;'t-5t}:ijfl
SUBTOTAL
$4i�12�8fi
ad,4o3 r
HOME OFFICE G&A (5.17 %)
pay
SUBTOTAL
g
c�JJ Sty'
OVERHEAD & PROFIT (10.0 %)
SUBTOTAL
$55,2 6 94
o0t 5 Iy i3
BONDS AND INSURANCE (.87 %)
$480-aq
aaS 41
TOTAL
5,,es?-n
J c 143 �?
S
ADJUSTED TO REFLECT ACTUAL COST
A :7�S DTD?REFL�C;irG1N1ELOSS BASE=N;SCHEDULEAIIALYSiS�: ^ "�','~
`� rH<;;��1 �•:�,i
�y "SEE,i?l7 l GHED .� _ » cti E01 -I .= ;`�t�.,t
:z r.�+w�.l:�r.*,'�.�i�.
.- . _ . _..... .. _.. ...._._... ... ....._� a _._. ._ .. -_ c. ...
UDIxED Z01 . CL1l D: E!?. NLY�IME�` D. EP1= 1L) E1IT, ITEMSATIDADl7STFD ,ORACIUALCOSTS,;': ^�;
r`�
REVISED BUDGET
Project Name: Owasso Public Works Authority
Project Number: C- 401146 -03
ORF -2B
Date: May 11, 1998
Loan Number: ORF -95 -002
S: \SHARESRF \0WASS0\0RF- 002.B1
MEMORANDUM
TO: HONORABLE CHAIR AND TRUSTEES
OWASSO PUBLIC WORKS AUTHORITY
FROM: F. ROBERT CARR, JR., P.E.
PUBLIC WORKS DIRECTOR
SUBJECT: FY97 -98 SUPPLEMENTAL BUDGET - REFUSE COLLECTION
DIVISION
DATE: June 11, 1998
BACKGROUND:
The FY97 -98 Public Works Department Refuse Collection Division budget line items for
operating supplies (61- 541 - 5220), vehicle maintenance (61 -541 -5260) and landfill tipping fees
(61 -541 -5391) are projected to exceed funds available for the remainder of the fiscal year. A
supplemental budget appropriation will be requested in order to meet the same level of service
presently provided in this division. Each of these line items are discussed below:
' Operating Supplies
The current operating supplies budget (Line item 61 -541 -5220) for the Public Works Refuse
Collection Division is $37,750 for FY97 -98. Included in this line item are supplies needed for
I' new polycarts used in our collection system and replacement /replace materials for repair of older
polycarts. Through June 3rd, expenditures for these operating supplies has been $47,661.41.
t The budget was prepared last year anticipating fewer new residential and yardwaste polycarts
than have been required for new services. In addition, replacements of older polycarts have
been occurring in higher numbers than projected.
' Vehicle Maintenance
The current vehicle maintenance budget (Line item 61- 541 -5260) is $21,200 for FY97 -98. To
date, $37,278.41 has been expended. It is projected that approximately $5,000 additional will
be required by the end of the fiscal year.
' The division primarily uses 1988 Lodal, 1992 Lodal and 1996 International vehicles. Each of
these vehicles have required repeated repair over the fiscal year. The continuous use of the 6-
and 10 -year old vehicles resulted in increased mechanical repairs over the amount anticipated
during the budget preparation.
REFUSE COLLECTIONS SUPPLEMENTAL BUDGET REQUEST
JUNE 11, 1998
PAGE 2
Landfill Tipping Fees
The current landfill tipping fees budget (Line item 61 -541 -5391) is $70,000. To date,
$72,166.32 has been expended. The increased expenditures is the result of an anticipated
reduction in rates that would have been, associated with a long -term disposal contract at the
landfill. Due to changes in personnel at the landfill, the contract has not been executed.
REQUEST:
Based on the above, a supplemental appropriation is requested. A total of $25,000 is requested
to meet current service levels. This budget recommendation has been reviewed by Ms Bishop, '
the City Manager and Public Works Director and all concur. It should be noted, however, that
the request focuses on funding unanticipated repair of vehicles and polycarts, as well as tipping
fees in excess of those anticipated. These expenses are not related to growth, thus there is not
a corresponding increase in revenues for the refuse service. While it is anticipated that there
will be an approximate $7000 in revenue over budget projections, the majority of the requested
supplemental appropriation will, if approved, come from reserves.
RECOMMENDATION:
The staff recommends Trustee approval of a supplemental appropriation to the FY97 -98 OPWA
Fund Public Works Department Refuse Collection Division budget in the amount of $25,000 for
the purpose of funding unanticipated expenses.