PROJECT: 96th Street North Roadway & Signalization Improvements
DATE PROJECT WAS INITIATED: June 2000
DATE PROJECT WAS COMPLETED: April 12, 2001
DEPARTMENT RESPONSIBLE FOR PROJECT: Public Works
STAFF COMMENTS: The project consisted of additional traffic lanes in the area of Owasso
Market from the U.S. Highway 169 southbound off ramp to about 450 west of North 119th East
Ave, intersection simalization at the off ramp and at 121St East Ave and stormwater drainage
improvements. In June 2000, the City Council awarded a contract to McGuire Brothers
Construction Company Inc in the amount of $530,431.90. The Notice to Proceed was delay
until August 4, 2000 to finalize funding_ agreements with all parties involved in the 96th St
corridor development. Three change orders were issued increasing the final contract amount to
$541,989.00 for cost overruns, and increasing the time by 55 days because of bad weather and
relocation of the RCB Center entrance. The City Council accepted the project on May 1 2001