HomeMy WebLinkAbout2000.12.06_Intersection Improvements0. PROJECT COMPLETION REPORT
PROJECT: Intersection and Signalization Improvements
DATE PROJECT WAS INITIATED: November 1999
DATE PROJECT WAS COMPLETED: December 6, 2000
DEPARTMENT RESPONSIBLE FOR PROJECT: Public Works
STAFF COMMENTS: The project consisted of roadway improvement and signalization of
intersections at 116th St N at N Garnett Rd and 76th St N at 129th East Aveā¢ signalization of two
intersections at 86" St N at 123rd East Ave; and roadway surface improvement on 86th St N
between Main St and Mingo Rd. In November 1999 the City Council awarded a contract to
Horizon Construction Company Inc in the amount of $1,268,128.64. Four change orders were
issued increasing the final contract amount to $1,497,504.06, and increasing the time by 43 days
A final inspection was held on December 6, 2000. The City Council accepted the project on
January 16, 2001. Funding was included in the 1998 bond issue
Phil Lutz
PROJECT COORDINATOR
Public Works