PROJECT: Community Center Renovation
DATE PROJECT WAS INITIATED: February 17, 2000
DATE PROJECT WAS COMPLETED: Community Center Roof - March 2000; Community
Center Carpet - April 2000.
DEPARTMENT RESPONSIBLE FOR PROJECT: Public Works
STAFF COMMENTS: On February 17, 1999 the City Council awarded a contract to Shelton
Metro Roofing in the amount of $75,800 for the purpose of re- roofing the Community Center.
One change order was issued amounting to $1141.43, bringing the total contract amount to
$76,941.43. Staff conducted several inspections during December 1999 and January 2000
because of roof leaks. All deficiencies were subsequently corrected and the contractor provided
a one -year maintenance bond. The City Council accepted the project on April 4, 2000. Funding
was included in the 1997 bond issue. On December 21, 1999 the City Council awarded a bid to
Mill Creek Carpet & Tile for carpet replacement in the Community Center dining room,
recreation room, lobby and offices. A Notice to Proceed was issued on March 25, 2000 after it
had been determined that all leaks in the roof had been corrected. The amount of the contract
was $29,760. The work was completed in April, with funding supplied by a Community
Development Block Grant.