HomeMy WebLinkAbout1999.10.22_Street ResurfacingPROJECT COMPLETION REPORT
PROJECT: Street Resurfacing - Atlanta (3`d to 11th). Carlsbad (3`d to 7th) & Beaumont; 129"' East
Ave (High School to 93`d St N)• I It' St (Main to Cedar)
DATE PROJECT WAS INITIATED: City Council awarded bid on October 20 1998
DATE INITIALLY SCHEDULED FOR COMPLETION: July 28, 1999
DATE ACTUALLY COMPLETED: Final Inspection held October 22, 1999
DEPARTMENT RESPONSIBLE FOR PROJECT: Public Works
STAFF COMMENTS:
On October 20, 1998 the City Council awarded a bid to Horizon Construction Co of Owasso OK
for the purpose of reconstruction of several streets. The total contract amount for the improvements
was $836,954.95. On December 15, 1998 Change Order #1 was approved by the City Council to
increase the contract amount by $19,270.94 for the use of quick -set flowable fill to stabilize the
subarade under 11th St because of ground water problems On May 4 1999 Change Order #2 was
approved by the City Council for $81,023.78 to reconcile the quantities on 11th St; add fabric
reinforcement, replace deteriorated storm drainage and reduce roadway repairs on Atlanta; and
reroute storm drainage away from 3`d St & Carlsbad to the east of Bailey Ranch Golf Course On
June 15, 1999 Change Order 93 was approved by the City Council for $27,726.18 to add the
walkbridee and sidewalk to the east side of N 129th east Ave from the High School to Camden Park
Change Order #4, approved on December 7 1999 relocated a 12" water line storm drain at 3`d &
Carlsbad and reconciled final construction quantities in the amount of $65,630.86. The final contract
amount for this project is $1,030,203.54. The project was accepted by the City Council on
December 7, 1999. Funding was included in the 1998 Bond Issue
Phil Lutz/Dwayne Henderson
PROJECT COORDINATOR
Streets
DEPARTMENT
PROJECT VANAGER
IZla jq�
DATE