HomeMy WebLinkAbout1999.10.15_Sports Park FieldsPROJECT COMPLETION REPORT PROJECT: Sports Park Four -Plex Fields and Soccer Fields DATE PROJECT WAS INITIATED: City Council awarded bid on February 17, 1999 DATE INITIALLY SCHEDULED FOR COMPLETION: September 5, 1999 DATE ACTUALLY COMPLETED: Final Inspection held October 15, 1999 DEPARTMENT RESPONSIBLE FOR PROJECT: Parks STAFF COMMENTS: On February 17 1999 the City Council awarded a bid to Frix & Foster Construction Co of Muskogee OK for the purpose of constructing a four -plex at the Owasso Sports Park. The total contract amount for the improvements was $267,308.00. On April 20, 1999 Change Order #1 was approved by the City Council to increase the contract amount by $7000 for the removal & replacement of unsuitable materials. Actual net cost was $4725. On July 20, 1999 Change Order #2 was approved by the City Council to add the construction of a new soccer field, increasing the contract by $30,000. On September 21, 1999 Change Order #3 was approved, adding 45 weather days to the contract because of the wet spring. The final contract amount for this project is $302,033. The project was accepted by the City Council on December 7, 1999. Funding was included in the 1998 Bond Issue. David Warren/Dwayne Henderson PROJECT COORDINATOR Parks DEPARTMENT �MMANAGER �2la l� DATE