HomeMy WebLinkAbout1999.10.15_Sports Park FieldsPROJECT COMPLETION REPORT
PROJECT: Sports Park Four -Plex Fields and Soccer Fields
DATE PROJECT WAS INITIATED: City Council awarded bid on February 17, 1999
DATE INITIALLY SCHEDULED FOR COMPLETION: September 5, 1999
DATE ACTUALLY COMPLETED: Final Inspection held October 15, 1999
DEPARTMENT RESPONSIBLE FOR PROJECT: Parks
STAFF COMMENTS:
On February 17 1999 the City Council awarded a bid to Frix & Foster Construction Co of
Muskogee OK for the purpose of constructing a four -plex at the Owasso Sports Park. The total
contract amount for the improvements was $267,308.00. On April 20, 1999 Change Order #1 was
approved by the City Council to increase the contract amount by $7000 for the removal &
replacement of unsuitable materials. Actual net cost was $4725. On July 20, 1999 Change Order
#2 was approved by the City Council to add the construction of a new soccer field, increasing the
contract by $30,000. On September 21, 1999 Change Order #3 was approved, adding 45 weather
days to the contract because of the wet spring. The final contract amount for this project is
$302,033. The project was accepted by the City Council on December 7, 1999. Funding was
included in the 1998 Bond Issue.
David Warren/Dwayne Henderson
PROJECT COORDINATOR