HomeMy WebLinkAbout1998.05.01_Restroom at Sports ParkPROJECT COMPLETION REPORT
PROJECT:___ Restroom #1 at Owasso Sports Park
DATE PROJECT WAS INITIATED: Mav 1997
DATE INITIALLY SCHEDULED FOR COMPLETION: April 16, 1998
DATE ACTUALLY COMPLETED: Final Inspection Held on Mav 1, 1998
DEPARTMENT RESPONSIBLE FOR PROJECT: Parks
STAFF COMMENTS:
The restroom was on i~nally put out to bid in June 1997, with only one bid being received in the
amount of $91,493. The City Council rejected that bid and authorized the staff to rebid the project.
The project was rebid in September 1997. The contract was awarded to Pettijohn Construction in
the amount of $85,405. Due to change orders, the final contract amount was $84 070. The CitX
Council accepted the project in May 1998. Funding was included in the Fy 1997-98 Capital
Improvements Fund.
David Warren
PROJECT COORDINATOR
Parks
DEPARTMENT
. ~~~~~ S~,S~~
PROJECT MANAGER
/- 1/- 9~
DATE