HomeMy WebLinkAbout1998.05.01_Restroom at Sports ParkPROJECT COMPLETION REPORT PROJECT:___ Restroom #1 at Owasso Sports Park DATE PROJECT WAS INITIATED: Mav 1997 DATE INITIALLY SCHEDULED FOR COMPLETION: April 16, 1998 DATE ACTUALLY COMPLETED: Final Inspection Held on Mav 1, 1998 DEPARTMENT RESPONSIBLE FOR PROJECT: Parks STAFF COMMENTS: The restroom was on i~nally put out to bid in June 1997, with only one bid being received in the amount of $91,493. The City Council rejected that bid and authorized the staff to rebid the project. The project was rebid in September 1997. The contract was awarded to Pettijohn Construction in the amount of $85,405. Due to change orders, the final contract amount was $84 070. The CitX Council accepted the project in May 1998. Funding was included in the Fy 1997-98 Capital Improvements Fund. David Warren PROJECT COORDINATOR Parks DEPARTMENT . ~~~~~ S~,S~~ PROJECT MANAGER /- 1/- 9~ DATE