HomeMy WebLinkAbout1996.11.05_City Hall Parking LotPROJECT COMPLETION REPORT PROJECT: Parking Lot for City Hall /Community Center DATE PROJECT WAS INITIATED: July 11, 1996 DATE INITIALLY SCHEDULED FOR COMPLETION: October 16, 1996 DATE ACTUALLY COMPLETED: Accepted November 5, 1996 DEPARTMENT RESPONSIBLE FOR PROJECT: Community Development STAFF COMMENTS: This project was designed to repair damage to portions of the base of the City Hall /Community Center parking lot and overlay the entire parking lot with two inches of asphalt The project was completed under a contract between the City of Owasso and APAC-Oklahoma of Tulsa The total contract cost of the project was $24.982 The Capital Improvements Budget included only $12,650 for the project. The City Council authorized the expenditure of an amount not to exceed $12.982 from the General Fund Budget to supplement the Capital Improvement David Warren PROJECT COORDINATOR January 9. 1997 DATE Community Development