HomeMy WebLinkAbout1996.11.01_76th Street OverlayPROJECT COMPLETION REPORT PROJECT: 76th Street Overlay DATE PROJECT WAS INITIATED:_ October 31, 1996 DATE INITIALLY SCHEDULED FOR COMPLETION: September 1995 DATE ACTUALLY COMPLETED: November 1. 1996 DEPARTMENT RESPONSIBLE FOR PROJECT: Public Works Department STAFF COMMENTS: This project Drovided an approximate two-inch asphalt overlay on 76th Street North between 129th East Avenue and U.S. 169. The City entered into an agreement with Tulsa County to complete this project The agreement required the City to purchase the asphalt and emulsion and the County to provide the equipment and labor The original cost estimate for the project was $70.000: the actual cost of the project was $23,300 73 Robert Carr PROJECT COORDINATOR January 9. 1997 DATE