HomeMy WebLinkAbout1994.04.18_Fire StationPROJECT COMPLETION REPORT PROJECT: Fire Station DATE PROJECT WAS INITIATED: March 27, 1992 DATE INITIALLY SCHEDULED FOR COMPLETION: March 1, 1994 DATE ACTUALLY COMPLETED: April 18, 1994 DEPARTMENT RESPONSIBLE FOR PROJECT: Fire Department STAFF COMMENTS: Planning by members of Owasso Fire Department began in September 1991. The architect for the project was hired on March 27, 1992 and construction began on August 11, 1993. The City accepted beneficial occupancy on April 18, 1994 and accepted the project as complete on July 19th, after all exterior items were completed. Total cost of the facility was $530,000.00. (That fip-ure, includes architect fees, land cost, construction cost, and the cost of extension of water and sewer lines. It does not include any cost of furnishings or office equipment.) Chief Bob Allen PROJECT COORDINATOR Fire Department DEPARTMENT ,�a �/ ,.9, - CITY NA ER October 7, 1994 DATE