HomeMy WebLinkAbout1994.04.18_Fire StationPROJECT COMPLETION REPORT
PROJECT: Fire Station
DATE PROJECT WAS INITIATED: March 27, 1992
DATE INITIALLY SCHEDULED FOR COMPLETION: March 1, 1994
DATE ACTUALLY COMPLETED: April 18, 1994
DEPARTMENT RESPONSIBLE FOR PROJECT: Fire Department
STAFF COMMENTS:
Planning by members of Owasso Fire Department began in September 1991. The architect for
the project was hired on March 27, 1992 and construction began on August 11, 1993. The City
accepted beneficial occupancy on April 18, 1994 and accepted the project as complete on July
19th, after all exterior items were completed. Total cost of the facility was $530,000.00. (That
fip-ure, includes architect fees, land cost, construction cost, and the cost of extension of water
and sewer lines. It does not include any cost of furnishings or office equipment.)
Chief Bob Allen
PROJECT COORDINATOR
Fire Department
DEPARTMENT
,�a �/ ,.9, -
CITY NA ER
October 7, 1994