HomeMy WebLinkAbout2007.11_E 86th St N Mingo St Intersection ImprovementsPROJECT COMPLETION REPORT PROJECT: E. 86th Street North Mingo Street Intersection Improvements DATE PROJECT WAS INITIATED: December 2006 DATE PROJECT WAS COMPLETED: November 2007 DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department STAFF COMMENTS: The East 86 Street North and Mingo Street Intersection project consists of widening the intersection and installation of traffic signals. In December 2006, the Oklahoma Department of Transportation (ODOT) awarded a contract to Becco Construction in the amount of $1,557,979.50. ODOT funded $1,235,200.00 towards the costs of construction. The City has contributed $861,924.00, which included engineering esign, utility relocation, right -away and 20% of the construction cost. Roger Stevens PROJECT COORDINATOR Public Works DEPARTMENT July 21" 2008 DATE Approved this 28th day of uly, 2008. Brenda Snow, Chairman