HomeMy WebLinkAbout2007.08_FY 07 Sports Park ExpansionPROJECT COMPLETION REPORT
PROJECT: Sports Park Expansion through FY -2007
DATE PROJECT WAS INITIATED: July 2004
DATE PROJECT WAS COMPLETED: Aueust 2007
DEPARTMENT RESPONSIBILITY FOR PROJECT: Parks Department
STAFF COMMENTS: This project consisted of the purchase of the 80 acres of
land south of the existing Sports Park, the entrance road base construction, half of the
construction of the base parking lot, and removal of existing structures on the site.
Additionally, construction of the remaining restroom at the existing Sports Park was
funded from this item. The total cost for this project is $2,062,418.00.
David Warren
PROJECT COORDINATOR
Parks
DEPARTMENT
January 21, 2008
DATE
Approved this 28th day of January, 2008.