HomeMy WebLinkAbout2009.07.21_N 129th E Ave Improvements® PROJECT COMPLETION REPORT
PROJECT: North 129th East Avenue Improvements
DATE PROJECT WAS INITIATED: October 1, 2007
DATE PROJECT WAS COMPLETED: July 21, 2009
DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department
STAFF COMMENTS: The North 129th East Avenue Improvements (from East 76th
Street North to East 94th Street North) involved the widening of the street to five lanes,
construction of new sidewalk, curb and gutter and sip-nalization at the High School/Mid -High
and the 6" Grade Center at an estimated cost of $8,680,000. On August 21, 2007, City
Council awarded the construction contract to Becco Construction in the amount
$8,320,902.80. Construction of the improvements have been completed, realizing an under
run of $128,336.88, for a revised contract amount of $8,192,565.92. Other expenditures
related to this improvement project included right of way acquisition, utility relocations,
engineering and design, and other professional services totaling $429,000; for a total project
cost of $8,620,898.
Rozer Stevens
PROJECT COORDINATOR
Public Works
DEPARTMENT
January 15, 2010
DATE
ApproXed this 25TH day of January, 2010.
Brenda Snow, Ch5irman