HomeMy WebLinkAbout2003.11.21_E 86th St N and Main Intersection ImprovementsPROJECT COMPLETION REPORT
PROJECT: E. 86" Street North and Main Intersection Improvements
DATE PROJECT WAS INITIATED: August 15, 2002
DATE PROJECT WAS COMPLETED: November 21, 2003
DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department
STAFF COMMENTS: The East 86th Street North and Main Street Intersection
project consists of road widening of the intersection and portions of surrounding streets
and upgrade of existing traffic signals. In July 2002 the Oklahoma Department of
Transportation (ODOT) awarded a contract to Horizon Construction in the amount of
$1,465,465.65. ODOT funded $1,002,057.27 toward the costs of construction The City
has contributed $546,250.00 . An audit to determine final project costs is currently being
performed by ODOT. Four potential change orders were issued during construction
increasing the final contract amount by approximately $44,000. It is anticipated that
ODOT will fund an additional $23,000 towards the final cost of construction Followin
the final audit, an additional amount of approximately $20,950 would be expected from
the City.
Ana C. Stagg
PROJECT COORDINATOR
Public Works
DEPARTMENT
July 22, 2004
DATE