PROJECT COMPLETION REPORT
PROJECT: E. 86th Street North and N. 145th East Avenue Intersection Improvements
DATE PROJECT WAS INITIATED: July 12, 2003
DATE PROJECT WAS COMPLETED: October 21, 2003
DEPARTMENT RESPONSIBILITY FOR PROJECT:_ Public Works Department
STAFF COMMENTS: The East 86th Street North and North 145th East Avenue
Intersection Improvements project consists of widening and signalization of the
intersection. On October 10 2003 Council awarded the construction contract to BECCO
Contractors Inc. for the amount of $757,046.10. Six change orders were issued during
construction in the amount of $36,056.83 for the relocation of utilities Additionally,
adjustments to the bid quantities were necessary at final payment to reflect actual
quantities provided during the construction of improvements Final construction cost for
the project was $793,102.93.
Ana C. Stagg
PROJECT COORDINATOR
Public Works
DEPARTMENT
PROJE& C ••'•1�
July 22, 2004
DATE