HomeMy WebLinkAbout2003.10.21_E 86th St N and N 145th E Ave Intersection ImprovementsI PROJECT COMPLETION REPORT PROJECT: E. 86th Street North and N. 145th East Avenue Intersection Improvements DATE PROJECT WAS INITIATED: July 12, 2003 DATE PROJECT WAS COMPLETED: October 21, 2003 DEPARTMENT RESPONSIBILITY FOR PROJECT:_ Public Works Department STAFF COMMENTS: The East 86th Street North and North 145th East Avenue Intersection Improvements project consists of widening and signalization of the intersection. On October 10 2003 Council awarded the construction contract to BECCO Contractors Inc. for the amount of $757,046.10. Six change orders were issued during construction in the amount of $36,056.83 for the relocation of utilities Additionally, adjustments to the bid quantities were necessary at final payment to reflect actual quantities provided during the construction of improvements Final construction cost for the project was $793,102.93. Ana C. Stagg PROJECT COORDINATOR Public Works DEPARTMENT PROJE& C ••'•1� July 22, 2004 DATE