PROJECT: Storm Siren Replacement
DATE PROJECT WAS INITIATED: November 1, 2003
DATE PROJECT WAS COMPLETED: December 17 2004
DEPARTMENT RESPONSIBILITY FOR PROJECT: Emergency Preparedness
STAFF COMMENTS: The Storm Siren Replacement Program involved the
replacement of the City of Owasso's existing storm siren system The project went to bid
in December of 2003. On April 6 2004 the project (which included 14 sirens on
concrete poles) was awarded to Total Radio of Tulsa Oklahoma for $205,194. Shortly
after the bid was awarded it was determined that the new school location at E. 76th Street
North and Memorial would not be in the coverage area As a result a change order was
processed to add an additional siren at a cost of $19,975. Additionally, underground
wiring of the poles, rather than overhead was performed by separate contract at a cost of
$8,914. This brought the project total to $234,083. The budget for this project was
$250,000.
./