HomeMy WebLinkAbout2005.08.16_E 96th St N and N 129th E Ave Intersection Improvementsc PROJECT COMPLETION REPORT
PROJECT: E. 96th Street North and N. 129th East Avenue Intersection Improvements
DATE PROJECT WAS INITIATED: July 23, 2003
DATE PROJECT WAS COMPLETED:_ August 16, 2005
DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department
STAFF COMMENTS: The nroiect consists of widp.ninv and n,- rm9n,-ni
at the E. 96th Street North
construction of approximately 857 linear feet of the Owasso Expressway. On July 23
2003, City Council approved a Development Agreement with The Home De opt for
construction of improvements in an amount of $1,442,000.00. One change order was
issued at project completion for $211,491.03 to reflect actual quantities provided and
scope changes made during construction Final construction cost for the project was
$1,653,491.03. Total project cost was $1,747,745.