PROJECT COMPLETION REPORT
PROJECT: E. 86th Street North Improvements
DATE PROJECT WAS INITIATED: September 2, 2003
DATE PROJECT WAS COMPLETED: June 15, 2004 * see supplemental below
DEPARTMENT RESPONSIBILITY FOR PROJECT: Public Works Department
STAFF COMMENTS: E. 86th Street North Improvements (from N 129th East Avenue to N.
14.5th East Avenue) which involves the wideniniz of the street to five lanes, construction of
new sidewalk, curb and Qutter and sitnalization at 8"' Grade Center. On August 5. 2003.
City Council awarded the construction contract to Becco Construction, Inc., Tulsa, OK in the
total amount of $2,472,065.20. Three change orders were issued during construction in the
amount of $188,447.44. Final construction cost for the project was $2,660,512.64.
Supplemental Information:
Including expenses for right of way acquisition, utility relocations, engineering and desk
and all other costs, the total project was $3,303,741 as of December 31, 2005. The original
Project Completion Report was approved by the Watchdog Committee on January 24, 2005.
One item related to right of way clearance, the demolition of a barn, remained outstanding.
The barn has been demolished and removed fiom the property at a cost of $15,500. Final
total expenditure for the E. l
Roger Stevens
PROJECT COORDINATOR
Public Works
DEPARTMENT
January 25, 2010
DATE
Approv d this 25TH day of January, 2010.
Bre da Snow, Chairrxrar°7"1